241108_ARCPaper1Annex1InternalAuditReportManagementActionFollowUp

Cairngorms Nation­al Park Authority

Intern­al Audit Report

Man­age­ment Action Fol­low-up Part 1202425

Novem­ber 2024

Con­tents:

  • Intro­duc­tion and back­ground — 1
  • Sum­mary of pro­gress — 2
  • Appendix 1: Action status by report — 4
  • Appendix 2: Sum­mary of out­stand­ing actions — 6
  • Appendix 3: Audit risk cat­egor­isa­tions — 21

Intro­duc­tion and background

Intro­duc­tion

As part of the intern­al audit pro­gramme we have under­taken a fol­low up review to provide the Audit & Risk Com­mit­tee with assur­ance that man­age­ment actions agreed in pre­vi­ous intern­al audit reports have been imple­men­ted appro­pri­ately. This report sum­mar­ises the pro­gress made by man­age­ment in imple­ment­ing agreed man­age­ment actions.

Scope

We have reviewed all open man­age­ment actions and liaised with Cairngorm Nation­al Park Author­ity staff to obtain an update on their imple­ment­a­tion pro­gress. This included man­age­ment identi­fy­ing actions which were no longer applic­able. For recom­mend­a­tions graded pri­or­ity 3 or above, we request evid­ence to val­id­ate com­ple­tion of any actions marked for clos­ure by management.

For all actions raised by the pri­or Intern­al Aud­it­or (BDO) we have aligned their risk assess­ments to the Azets risk grad­ing struc­ture (per Appendix 3).

Action for Audit & Risk Committee

The Com­mit­tee is asked to note the pro­gress made by man­age­ment in imple­ment­ing agreed man­age­ment actions. The Com­mit­tee is also asked to con­sider and approve those actions for which revised times­cales have been provided by man­age­ment (these are detailed at Appendix 2).

Sum­mary of progress

The table below shows the move­ment in the audit actions in the peri­od from April 2024 to Novem­ber 2024:

Num­ber of Actions
Open actions brought forward28
Actions added to tracker7
Total actions to follow-up35
Actions closed10
Actions Super­seded1
Open actions car­ried forward24

Status of Actions as at Novem­ber 2024

(Pie chart show­ing 5 Com­plete, 10 Par­tially Com­plete, 1 Super­seded, and 19 Incom­plete actions)

We have con­firmed that 10 actions (29%) were com­peted in the peri­od to Novem­ber 2024. In addi­tion, one action is recom­men­ded for clos­ure as it has been super­seded (3%).

19 actions (54%) have been assessed as par­tially com­plete and five (14%) are incom­plete. Fur­ther detail on all out­stand­ing actions is included at Appendix 2.

We recom­mend that man­age­ment take a strong focus on clear­ing aged items in the com­ing months. We recom­mend pri­or­it­ising the most aged items and those that are grade 3 and grade 4. Atten­tion should then be paid to those remain­ing actions that have passed their ori­gin­al due date and those which will pass their due date for com­ple­tion over the next period.

A sum­mary of the status of actions by report is shown at Appendix 1.

Status by Grading

(Bar chart show­ing the num­ber of com­plete, incom­plete, par­tially com­plete, and super­seded actions for each grade (14))

Appendix 1: Action status by report

Report titleCom­pletePar­tially com­pleteIncom­pleteSuper­sededTotal
Grant Fund­ing & Management11
201617 sub-total111
Busi­ness Con­tinu­ity Planning11
201819 sub-total111
FOISA and EIR Requests11
201920 sub-total111
Data Man­age­ment112
202021 sub-total1112
LEAD­ER Programme11
Fin­an­cial Man­age­ment and Reporting11
Assur­ance Map­ping of Major Projects22
Cyber Secur­ity Review22
ICT Strategy44
Peat­land Action Pro­gramme Set Up11
202122 sub-total189
Per­form­ance Management112
Data Man­age­ment112
Payroll and Expenses11
202223 sub-total3216
Expendit­ure and Creditors112
Risk Man­age­ment112
Health and Safety314
Her­it­age Horizons22
Pro­cure­ment347
202324 sub-total664116
Grand totals10195135

Appendix 2: Sum­mary of out­stand­ing actions

Report / ActionRecom­mend­a­tionAction Own­erGradeOri­gin­al times­caleRevised times­caleUpdate Novem­ber 2024Status
201617 Grant Fund­ing and ManagementWe recom­mend that the Grant Toolkit is com­pleted, encom­passing all pro­cesses in place for the award­ing, record­ing and mon­it­or­ing of grant funding.Dir­ect­or of Cor­por­ate ServicesMedi­um (Grade 2)Sep 2017Mar 25Grant tem­plates have been developed, includ­ing an award doc­u­ment and terms & conditions.Par­tially Complete
201819 Busi­ness Con­tinu­ity PlanningWe recom­mend that CNPA devel­ops a test­ing plan/​schedule for BCP which should be reviewed reg­u­larly to ensure a stra­tegic approach to test­ing is developed and implemented.Dir­ect­or of Cor­por­ate ServicesMedi­um (Grade 2)Nov 2019Mar 25BCP is in need of update.Incom­plete
201920 FOISA and EIR RequestsWe recom­mend CNPA review and update its Pub­lic­a­tion Scheme.Inform­a­tion ManagerLow (Grade 1)Dec 20Mar 25Pub­lic­a­tion scheme will be updated in par­al­lel with the web devel­op­ment project.Par­tially Complete
202021 Data ManagementWe recom­mend that once the Author­ity have received the feed­back from their DPOaaS pro­vider, they cre­ate a sub­ject access request pro­ced­ure, or doc­u­ment the pro­cess with­in an exist­ing procedure.Office Ser­vices ManagerMedi­um (Grade 3)Jun-21Dec 24This work is with­in the remit of Inform­a­tion Manager.Par­tially Complete
202122 Assur­ance Map­ping of Major ProjectsMan­age­ment should put in place a pro­ject plan for imple­ment­a­tion of the new pro­ject man­age­ment approach.Dir­ect­or of Cor­por­ate ServicesMedi­um (Grade 2)Sep-22Sep 25We have developed and imple­men­ted a new pro­ject man­age­ment and report­ing system.Par­tially Complete
202122 Cyber Secur­ity ReviewWe recom­mend that CNPA should per­form a risk assess­ment as well as a gap ana­lys­is of the cur­rent tech­no­logy, policy and busi­ness environment.Inform­a­tion Sys­tems ManagerMedi­um (Grade 3)Aug 22Apr 25While we are mind­ful of risks as part of the course of our day-to-day man­age­ment of our IT resources.Par­tially Complete
202122 Cyber Secur­ity ReviewWe recom­mend that CNPA estab­lish pro­ced­ures for hand­ling cyber secur­ity events.Inform­a­tion Sys­tems ManagerMedi­um (Grade 2)Dec-22Aug 25While we are mind­ful of risks as part of the course of our day-to-day man­age­ment of our IT resources.Par­tially Complete
202122 ICT StrategyWe recom­mend that the next devel­op­ment of the IT and Data Strategy includes a fin­an­cial strategy.Dir­ect­or of Cor­por­ate ServicesMedi­um (Grade 2)Sept 23Dec 25The Authority’s stra­tegic approach to ICT is under consideration.Par­tially Complete
202122 ICT StrategyWe recom­mend that man­age­ment expli­citly doc­u­ment approvals of strategies with­in minutes of meetings.Dir­ect­or of Cor­por­ate ServicesMedi­um (Grade 2)Mar-23Dec 25All strategy and policy doc­u­ments are presen­ted to both the Seni­or Man­age­ment Team and the Board.Par­tially Complete
202122 ICT StrategyWe recom­mend that the action plan with­in the IT and Data Strategy is updated to include action own­ers and deliv­ery dates.Inform­a­tion Sys­tems ManagerMedi­um (Grade 3)Jun-22Dec 25The IT oper­a­tion­al plan will, in future, fol­low nat­ur­ally from the ICT strategy.Par­tially Complete
202122 Peat­land Action Pro­gramme Set UpMan­age­ment should doc­u­ment the risks asso­ci­ated with the full-ser­vice approach and put mit­ig­at­ing con­trols in place.Dir­ect­or of Nature and Cli­mate ChangeHigh (Grade 4)Dec-22Mar 25The SLA developed by our law­yers has been cir­cu­lated and tested with land managers.Par­tially Complete
202223 Data ManagementWe recom­mend that CNPA review the cur­rent policy suite that is in place and devel­op and imple­ment policies that address the fol­low­ing policy areas:Deputy Chief ExecutiveMedi­um (Grade 3)Dec 23Apr 25The Inform­a­tion Man­ager is work­ing on this as part of his review of policies.Par­tially Complete
202223 Per­form­ance ManagementWe sup­port management’s approach to devel­op­ing a dash­board to sup­port more fre­quent scru­tiny and chal­lenge by seni­or management.Gov­ernance, Data and Report­ing ManagerMedi­um (Grade 2)Dec-22Dec 25Our work on cor­por­ate per­form­ance man­age­ment is ongoing.Par­tially Complete
202223 Expendit­ure and CreditorsCNPA should pro­mote the import­ance of the stand­ard­isa­tion of doc­u­ment­a­tion kept for each pur­chase, and require that for each com­mit­ment of expendit­ure the fol­low­ing should be doc­u­mented and maintained:Fin­ance ManagerGrade 2Mar 24Mar 25The import­ance of segreg­a­tion of duties was dis­cussed dur­ing staff workshops.Par­tially Complete
202324 Risk ManagementMan­age­ment should imple­ment oper­a­tion­al risk registers to ensure that oper­a­tion­al risks related to the day-to-day activ­it­ies of the organ­isa­tion are recor­ded and mon­itored on a reg­u­lar basis.Deputy Chief ExecutiveGrade 3Dec 23Mar 25Risk registers are now in place for IT, Comms and C2030Par­tially Complete
202324 Health and SafetyWe recom­mend that the Health and Safety Policy and all sup­port­ing policies are sub­ject to reg­u­lar review to ensure that they reflect the cur­rent legis­lat­ive requirements.Facil­it­ies ManagerGrade 3Apr-24Mar 25This is in progress.Par­tially Complete
202324 Pro­cure­mentCNPA should devel­op a new Pro­cure­ment Strategy and sup­port­ing policies and pro­ced­ures as soon as possible.Deputy Chief Exec­ut­ive with Head of Fin­ance and Cor­por­ate Operations4Sept 24TBCPro­cure­ment strategy now refreshed and approved by ARC.Par­tially Complete
202324 Pro­cure­mentCNPA should pre­pare and pub­lish annu­al pro­cure­ment reports, main­tain a con­tract register and pro­duce a pro­cure­ment expendit­ure report.Deputy Chief Exec­ut­ive with Head of Fin­ance and Cor­por­ate Operations3Dec 24TBCThe pro­cure­ment strategy has now been updated and agreed, and now sets out any reporting.Par­tially Complete
202324 Pro­cure­mentCNPA should under­take a full review of the pro­cure­ment doc­u­ment­a­tion held for each supplier.Head of Finance4Sept 2024 onward, accord­ing to the agreed action plan.TBCAction plan provided to ARC.Par­tially Complete
202324 Pro­cure­mentMan­age­ment should seek to devel­op tem­plates which set out the stages of the pro­cure­ment journey.Head of Finance4Mar 25N/AIncom­pleteIncom­plete

Appendix 3: Audit risk categorisations

Man­age­ment action grades

  • 4: Very high risk expos­ure — major con­cerns requir­ing imme­di­ate seni­or atten­tion that cre­ate fun­da­ment­al risks with­in the organisation.
  • 3: High risk expos­ure — absence / fail­ure of key con­trols that cre­ate sig­ni­fic­ant risks with­in the organisation.
  • 2: Mod­er­ate risk expos­ure — con­trols are not work­ing effect­ively and effi­ciently and may cre­ate mod­er­ate risks with­in the organisation.
  • 1: Lim­ited risk expos­ure — con­trols are work­ing effect­ively, but could be strengthened to pre­vent the cre­ation of minor risks or address gen­er­al house­keep­ing issues.

© Azets 2024. All rights reserved. Azets refers to Azets Audit Ser­vices Lim­ited. Registered in Eng­land & Wales Registered No. 09652677. VAT Regis­tra­tion No. 219 0608 22.

Registered to carry on audit work in the UK and reg­u­lated for a range of invest­ment busi­ness activ­it­ies by the Insti­tute of Chartered Account­ants in Eng­land and Wales.

×