25/03/2022 - CNPA BdPaper 3Annex2 Corporate Plan KPIs
KPI Reporting
CAIRNGORMS NATIONAL PARK AUTHORITY Formal Board Paper 3 Annex 2 25th March 2022
Indicator | Target | Update | Rating |
---|---|---|---|
Conservation and Land Use | |||
Area of new native woodland | 1000 ha pa | The rate of approved afforestation across the last five years, achieved through a mixture of natural regeneration and planting, has on average exceeded the target rate of 1000 ha per year. Early indications, based on draft woodland creation proposals shaping up on various estates across the CNP, suggest the average annual rate of afforestation will increase significantly across the next five year period. | Green |
Area of peatland restoration | 1000 ha pa | In 2021⁄22 the CNPA Peatland Action programme is currently on track to deliver around 550ha of peatland restoration management across 10 sites on 7 estates by March 2022. The target for this year is 557ha. Precise measurements are not yet available but the team is confident that the work done to date will be very close to target. The current mild winter has enabled peatland restoration to continue throughout much of January. If mild conditions continue into February then around 700ha of peatland restoration management could be achieved by end March which would exceed target agreed with Scottish Government to underpin funding, while below the original target adopted at the commencement of this Corporate Plan . | Amber |
Deer density across Deer Management Groups | Reductions towards 10 per km² or less | Discussions with South Deeside and North Angus DMG and South Grampian DMG are ongoing as to the scope of their Strategic Land Use Plans and how these should be developed. The aim is to commence gathering data in April 2022. This may be done by consultants or through the combined internal resources of the DMGs and CNPA. The development of Strategic Land Use Plans for SDNA and SG DMGs will be taken forward within the Heritage Horizons programme. West Grampians DMG have already agreed the scope and content of their plan and have a consultant, an independent Chair and a Steering Group in place. | Amber |
Number of Capercaillie | 1200 by 2022 | Target will not be met. Full national survey results due in 2022 but other surveys suggest population has declined seriously from the 1100 birds estimated 2016 | Red |
Numbers of wildlife crime incidents in the Park | Zero per annum | Wildlife crime continues to be a serious issue in the Park. We continue to work with Nature Scot, Police Scotland and Raptor study group and BTO tag development is still ongoing. In the meantime three alternative tags have been fitted on to golden eagles in the park during the 2021 breeding season. All birds are still in, or in close proximity to, the Park. Cairngorms Nature Strategy Group are considering possible actions to further address this issue and take forward raptor conservation in CNP. | Red |
Length of path upgraded or extended | 20km upgraded by 2022 6km new path by 2022 | 51.8 km of path upgraded by Mountains & People project (ended Jan 2021) 6.5 km of new path constructed along Speyside Way Extension & Seven Bridges path Ballater. Further improvements to the route at Grantown, Kincraig have secured funding support from NatureScot with possible upgrade 2022 | Complete |
Tourism Impact | Increase economic impact of visitors to eastern and southern CNP from 21% to 25% of total visitor economy by 2022 | STEAM data for 2019 indicates that economic impact of visitors to eastern and southern CNP to be 21.6% of the total visitor economy. This is slightly above the baseline figure but a decline on 2017 (22.8%) and 2018 (21.9 %) STEAM data for 2020 still being evaluated | Red |
Completions of John Muir Awards | 2500 awards per annum and ensure at least 20% from disadvantaged backgrounds | Some 2684 people completed a John Muir Award in and around Cairngorms in 2019. JMA currently on hold as we come out of Covid-19 lockdown. In 2020 a total of 972 John Muir Awards were completed, and 832 in 2021, considerably down on normal due to Covid-19 restrictions. | Amber |
Number of Volunteer Rangers | Minimum 8 volunteer rangers trained per annum | Project has trained 38 Volunteer Rangers with most now re-engaging as we come out of Covid-19 lockdown. Nine additional Volunteer Rangers will be training Spring 2022 | Green |
5 yr Visitor Survey 2020 | Increase Social Grade ‘C2, D, E’ visitors from 18 to 20% | Full survey data indicates 27% C2, D & E with 97% response rate — significantly higher than 2015 18% with 94% response rate | Green |
Number of affordable houses delivered as a proportion of total houses delivered per annum | 200 new affordable houses by 2022 | The CNPA has granted consent (including consent by appeal) for 578 affordable homes since 31st March 2018. 375 affordable units are part of the planning permission in principle issued for An Camus Mor. Of the 203 other affordable homes given consent, 34 are completed and 54 are in construction. A further 22 affordable units have been completed on consents issued before 31 March 2018, meaning that 56 affordable homes have been completed. A Community Housing Project in Tomintoul is in construction with 12 units and a planning application for 15 community owned affordable houses in Braemar is progressing. | Green |
Number of people involved in community activity for the first time through LEADER support | By end of Programme = 80 | LEADER Programme Monitoring and Evaluation currently reporting 227 people have become involved in community projects for the first time through the programme’s interventions. | Achieved |
Business satisfaction with CNPA | Maintain or increase from 17⁄18 average (5.44 out of 10) | Murray to complete | |
Staff Turnover | Staff Turnover level not more than 10% | Turnover to April 2021 — September 2021 was 6% (excluding short term contracts, 5 leavers out of headcount of 83 (sept 2021) ). In the period October 2021 to March 2022, turnover is forecast to be approx.. 4% | Green |
Recruitment | Successful recruitment to all vacant posts | 3 posts were not recruited at first launch. Two had to be re-specified and were then successfully appointed. One went back to recruitment in the same format. This post is still live | Amber |
Staff Absence | Staff absence levels below 5 days per person per year and no more than 3 absences in a 12 month period | April — June 2021. Absence (excl covid)- 0.43 days, (incl covid) 0.46 days. Sickness absence of 0.27 days. July — September 2021. Absence (excl covid)- 0.72 days, (incl covid) 0.78 days. Sickness absence of 0.49 days October – December 2021 Absence (excl covid)- 1.07 days, (incl covid) 1.14 days. Sickness absence of 0.96 days | Green |
Causes of absence | NO work related causes of absence | April — December 2021: — no work related causes of absence | Green |
Case load | Maximum 2 incidences of formal HR caseload in a rolling 12 month period | April — December 2021: — no formal caseload | Green |
Complaints | 100% of complaints on log responded to within good practice time frames. | April 2021 — February 2022: — 17 complaints. 6 dealt with at frontline resolution stage – all within time; I was an external matter; 10 dealt with at investigation stage, of which 9 were on time, and I was on time from follow up request seeking clarification. | Green |
FOI/EIR requests | Responses to all FOI and EIR requests within 20 days | At end of Q3 2021 – 22 — 92% of information requests were responded to within 20 days a total of 2 requests were responded to outside of statutory deadlines one due to an administrative error and one due to staff absence | Amber |
H&S | Health and Safety — 0 RIDDOR reportable injuries. Maximums of 0 major injury, I minor injury and 3 near misses. | 0 RIDDOR reportable injury 0 Major Injury 0 minor injury | Green |
Audit | No more than 2 top priority audit recommendations in year. | With two internal audit reviews still to have final reports submitted, there are no top priority audit recommendations over the year. | |
Income | Total Income in line with budget | Total income back in line with budget following reversal of proposed 2% resource grant saving | |
Core Budget | Core expenditure in line with or below budget: | Core budgets all either in line or below budget. In year budget amendments made to reallocate resource from core areas of expenditure to support operational plan investment in delivery of strategic outcomes. | |
Operational Plan Budget | Operational Plan in line with or exceeding budget | Operational Plan budgets with exception of peatland programme expenditure all in line with or in excess of original budget, with additional investment supported by reallocation of budget from areas of core running costs. Peatland programme funding amendments agreed in advance with Scottish Government. | |
Forecast Outturn break even | Final financial net outturn within +1% to ‑2% of total income including Scottish Government grants. | Continue to forecast financial outturn position within established range. | |
Next Year income | Next year income in line or above forward forecasts | 2022⁄23 forecast income currently ahead of initial budget forecasts, with uncertainty remaining at time of this update around peatland programme resource funding and nature restoration investment to replace Biodiversity Challenge Funding. | |
Operational Plan Leverage | Operational plan investments secure external financing of 3 times value of CNPA total investment. | Significant external funding secured for Heritage Horizons Programme and Cairngorms Capercaillie Project, together with additional funding in place for other project activities, continue to secure delivery of this objective. | |
Carbon emissions: reduction in CNPA generated carbon emissions | Target 3% annual reduction in baseline emissions = 150 estimated tonnes CO2 in 2007⁄08 (start of modelling). This measure recalculated to fit with broader reporting tool implemented by Scottish Government. | Our last reported figures for 2020/21gave total emissions of 53 tCO2e, only 35.3% of the baseline figure and therefore almost a 65% reduction from that level since 2007⁄08, well ahead of the annual target. (Prior year level, 2019⁄20 with only minimal COVID19 interruption to operations = 85 tCO2e.) Final emission figures for March 2022 will be known in April 2022. Quarterly monitoring of different emission items continuing throughout the year. Vehicle mileage increased considerably in current year compared to previous year when full lockdown was in place. Other items of monitoring reasonably constant to prior year. This points to a likely overall increase in emissions in the year, however, it must be noted the emission results in the year to March 2021 was an exception rather than norm due to the lockdown restrictions in place for staff movement. Scottish Government introduced in March 2021 submission a calculation for Homeworking emissions based on number of FTE working from home during lockdown. It is currently unknown whether this is continuing in the March 2022 submission – the calculation is built-in to the submission data page which is made available September/October | Green |
Equalities: equal pay assessments on CNPA salaries | Pay assessments show equal pay between male and female employees | April 2021 – 17.44. High comparative to Scotland (10.4% in 2020), but on downward trajectory on a continued downward trajectory of the corporate plan period . | Amber |