Item6AADulnainBridgeHousing20180221DET
CAIRNGORMS NATIONAL PARK AUTHORITY
Planning Committee Item 6 11/10/2019
CAIRNGORMS NATIONAL PARK AUTHORITY
DEVELOPMENT PROPOSED:
Erection of 18 houses, upgrade of access at Land 40M NE of Rose Cottage, Dulnain Bridge
REFERENCE:
2018/0221/DET
APPLICANT:
Highland Housing Alliance
DATE CALLED-IN:
13 June 2018
RECOMMENDATION: Approve subject to conditions
CASE OFFICER:
Stephanie Wade, Planning Officer
CNPA Planning Committee Application Site
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
CAIRNGORMS NATIONAL PARK AUTHORITY
Planning Committee Item 6 11/10/2019
SITE DESCRIPTION, PROPOSAL AND HISTORY
Site Description
The application site comprises approximately 1.09 hectares of grassland, located on the western edge of the settlement of Dulnain Bridge, abutting the northern side of the A938 and wrapping around the residential property Rose Cottage. The remainder of the site is bound by the mature woodland of Dulnainbridge Plantation. The site is relatively flat in an east to west direction with the ground surface inclining gradually to the northern site boundary where it extends at a steeper gradient beyond through the plantation. A drainage ditch runs along the northern boundary flowing eastwards to the site boundary where it terminates at a buried pipe beneath the A938.
The site is not covered by any specific environmental designations. The adjacent Dulnainbridge Plantation is recorded within the Ancient Woodland Inventory. The site contains areas of medium probability of surface flooding.
Proposal
- The drawings and documents associated with this application are listed below and are available on the Cairngorms National Park Authority website unless noted otherwise: http://www.eplanningcnpa.co.uk/online- applications/applicationDetails.do?activeTab=summary&keyVal=PA9NEHSI0CA00
Title | Drawing Number | Date on Plan* | Date Received |
---|---|---|---|
Plans: | |||
Location Plan | P‑006 Rev.Α | 24 July 2019 | 26 July 2019 |
Overall Site Plan | P‑001 Rev.Κ | 06 September 2019 | 06 September 2019 |
Site Layout Phase I Plan | P‑010 Rev.G | 06 September 2019 | 06 September 2019 |
Site Layout Phase 2 Plan | P‑011 Rev.F | 16 August 2019 | 23 August 2019 |
Site Section Plan | P‑012 | 12 July 2019 | 26 July 2019 |
Proposed Roads Layout Plan | 910 Rev.7 | 23 July 2019 | 23 August 2019 |
Landscape Proposals Plan | ННА 105.19 SL- | 27 June 2019 | 26 July 2019 |
01 Rev.E | |||
Tree Protection Plan | 106801-TPP-C3 | 25 July 2019 | 26 July 2019 |
Proposed Footpath Widening Plan | 1100 Rev.2 | 18 July 2019 | 26 July 2019 |
Proposed Footpath Layout Leading Into Dulnain Bridge Plan | 918 | 18 July 2019 | 26 July 2019 |
Plot Sections Plan | SK-03 Rev.1 | 11 July 2019 | 26 July 2019 |
Swept Path Analysis Refuse Vehicle Plan | 913 Rev.2 | 27 June 2019 | 26 July 2019 |
Swept Path Analysis Plot Driveways Plan | 1101 Rev.3 | 18 July 2019 | 26 July 2019 |
Proposed 30mph Signage Plan | 930 Rev.1 | 28 June 2019 | 26 July 2019 |
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
Title | Drawing Number | Date on Plan* | Date Received |
---|---|---|---|
3D Visibility Splay Plan | 1102 Rev.3 | 05 September 2019 | 05 September 2019 |
Proposed Ditch Diversion Plan | 1103 Rev.2 | 23 July 2019 | 26 July 2019 |
Proposed Rising Main Layout Sections and Details Plan | 923 Rev.2 | 23 July 2019 | 26 July 2019 |
Proposed Drainage Layout Plan | 920 Rev.6 | 15 August 2019 | 19 August 2019 |
Amended Floor Plans, Section & Elevations- 2 Bedrooms (s) | P‑002 Rev.D | 27 June 2019 | 26 July 2019 |
Amended Floor Plans, Section & Elevations- 3 Bedroom (s) | P‑003 Rev.D | 27 June 2019 | 26 July 2019 |
Amended Floor Plans, Sections & Elevations- 4 Bedrooms (D) | P‑004 Rev.D | 27 June 2019 | 26 July 2019 |
Amended Floor Plan, Section & Elevations- 3 Bedroom (D) | P‑005 Rev.D | 27 June 2019 | 26 July 2019 |
Proposed Site Levels Plan | 914 Rev.1 | 14 March 2019 | 22 March 2019 |
Cut and Fill Layout Plan | 908 Rev.1 | 08 June 2018 | 26 June 2018 |
Road Construction Details | 906 | 30 April 2018 | 26 June 2018 |
Sewers Construction Standard Details | 907 | 01 May 2018 | 26 June 2018 |
Tree Constraint Plan | 812701 | 07 June 2018 | 26 June 2018 |
Supporting Documents: | |||
Design and Supporting Statement | 01 June 2018 | 26 June 2018 | |
Bat Roost Inspection Survey | 04 June 2018 | 26 June 2018 | |
Tree Schedule | 9793 | 07 June 2018 | 26 June 2018 |
Tree Survey Report | 9793 | 07 June 2018 | 26 June 2018 |
Visual Information | 26 June 2018 | ||
Maintenance Statement- Boundary Ditch | 181185-GRD | 22 March 2019 | |
Ground Maintenance Schedule | 22 March 2019 | ||
Ecology Supplementary Report | 01 October 2018 | 22 March 2019 | |
Dulnain Bridge Water Vole Memo | 14 June 2019 | 17 June 2019 | |
Drainage Impact Assessment | 1⁄181185 Rev.B | 01 July 2019 | 26 July 2019 |
Arboricultural Impact Assessment and Method Statement | 1068 | 25 July 2019 | 26 July 2019 |
Reptile Survey Report by Alba Ecology Ltd | 01 June 2019 | 26 July 2019 | |
Additional Supporting Statement | 2017-085 | 26 July 2019 | |
Highland Housing Alliance Tenancy Management Statement | 26 July 2019 | ||
Soft Landscape Works- 5 year | Rev. C | 23 July 2019 | 26 July 2019 |
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
Title | Drawing Number | Date on Plan* | Date Received |
---|---|---|---|
Maintenance Régime | |||
IYr Incl. 30CC Calculations | 15 August 2019 | 19 August 2019 | |
200Yr Incl. 30CC Calculations | 15 August 2019 | 19 August 2019 | |
30Yr Incl. 30CC Calculations | 15 August 2019 | 19 August 2019 | |
SUDS Basin Impermeable Areas Calculations | 23 May 2019 | 19 August 2019 | |
Post Development Runoff Calculations | 22 May 2019 | 19 August 2019 | |
SUDS Basin Calculations | 22 May 2019 | 19 August 2019 |
*Where no specific day of month has been provided on the plan, the system defaults to the 1st of the month.
- This application seeks planning permission for the erection of 18 dwellinghouses with associated access, drainage, service and landscaping works. The development includes a mix of detached and semi-detached houses ranging between one and one and half- storey units. The dwellinghouses are all proposed to be affordable units with a combination of 10 mid-market rent for Highland Housing Alliance and 8 Council owned units. The housing schedule is as follows:
Number of Units | Number of Storeys | Accommodation Type | Number of bedrooms |
---|---|---|---|
8 | One and a half | Semi-detached | 2 |
8 | One and a half | Semi-detached | 3 |
1 | Single Storey | Detached | 3 |
1 | Single Storey | Detached | 4 |
Following the original submission, the application has been subject to a number of amendments to the details of the scheme, such as the drainage measures, road, parking and footpath layouts and landscaping. The amendments have been sought to try and overcome the concerns raised by consultation respondents throughout the progression of this application. The following paragraphs describe the latest submission details for the proposal.
All 18 dwellings have been designed with dual pitched roofs, incorporating porches and a combination of dormer and roof light features. Proposed finishes are white roughcast walls with sections of Eternit Cedral weatherboarding, dark grey Aluclad windows and grey roof tiles. Solar PV panels are proposed to be installed on the roofslopes of the dwellinghouses. The application Design and Supporting Statement states that the four house types have been designed in accordance with the Firm Foundations Design Brief, prepared by Highland Housing Alliance and the design guide for Housing for Varying Needs.
Access to the site is proposed to utilise the existing site access, which was approved under the 2004 application. The existing access bellmouth is to be retained with a single internal road leading into the site and continuing in a westerly direction to provide access to the dwellings, which will be constructed linear to the internal access road forming a cul-de-sac layout. Two turning heads (I temporary) are proposed to be constructed and a singular lane leads off the main internal site road to the east to
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
provide vehicular access to dwelling plots 16, 17 and 18. Pedestrian pavements abut the internal road throughout the site and continue to the east, linear, but set back from the A938 to provide pedestrian access into the village. The scheme is proposed to be constructed in two phases and the phase I hardcore turning area is proposed to be removed upon completion of the second phase construction when the permanent turning head is installed.
A total of 42 car parking spaces are proposed to be installed within the site. Each dwelling is proposed to be served by two parking spaces each to be located within the curtilages of the individual dwellings. The 6 visitor parking spaces are proposed to be sited in two blocks adjacent to the northern side of the internal road.
The development is proposed to be serviced by a new foul pump station, which is proposed to be located adjacent to the A938 within the eastern side of the site. Private connections are proposed to be made from each unit to a new gravity sewer within the internal access road. The proposed surface water arrangements include the use of permeable site materials and a detention basin. All roof water is proposed to be drained into a surface water sewer, which will then discharge into the detention basin located within the eastern area of the site, adjacent to the proposed pump station.
The existing, open drainage ditch, which runs adjacent to the northern site boundary is proposed to be enclosed. A I metre wide cut-off drain system with water draining into a 225mm diameter, half perforated collector pipe is proposed, with the drain terminating via a controlled discharge to the existing watercourse by a hydro brake manhole. The boundary of the domestic curtilages for the northern site properties have been amended to allow for a I metre wide maintenance access to the drain channel.
Each dwelling is proposed with its own private garden area to be enclosed by 1.8 metre high timber fence and a 1.2 metre high timber picket fence is proposed to be erected along some of the other curtilage boundary lines of each property. The remainder of the site is proposed to be grassed with tree planting proposed in clusters around the site, which include: Silver birch, Rowan, Aspen, Alder, and Pine. 13 existing trees within the eastern site corner are proposed to be removed. Proposed shrub planting throughout the site includes: Hazel, Holly, Juniper, Heather, Blaeberry, Broom and Bog Myrtle.
The application is supported by the following information:
a) Design and Supporting Statement, additional supporting statement and Highland Housing Alliance Tenancy Management Statement: these documents provide an outline of the framework that informed the design development of the proposed scheme. The documents consider the site constraints, policy framework, and summarises the individual elements of the scheme including road access, drainage, house design and landscape. The additional supporting statement provides further clarification regarding the evolution of the design concept of the scheme. The Highland Housing Alliance Tenancy Management Statement provides justification for the design elements of the dwellinghouses relating to the siting of the car parking, front door locations, garden orientation and boundary fence heights. The document confirms that all
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
elements have been designed to provide an enhancement to the quality of living to their residents.
b) Ecological reports including: Bat Roost Inspection Survey, Ecology Supplementary Report, Water Vole Memo and Reptile Survey Report: A preliminary Bat roost inspection survey was undertaken by Coachman Bat Consultancy with the findings included within the report dated 04 June 2018. The survey assessed trees within the site and one tree outwith the site for their potential for roosting suitability. The survey concluded that the trees surveyed were considered to provide negligible or very limiting roosting potential and there was no evidence of roosting bats. A supplementary ecology report dated October 2018 providing an ecology assessment update to the previous field work undertaken for bat and reptiles. The survey recommended that a dawn emergence survey for bats would be required and noted that the bat foraging routes were unlikely to be affected by the development. The survey also recommended that the reptile survey is repeated to provide further data. A Water Vole survey was undertaken and submitted in support of the application to determine whether the proposed ditch works would impact on any water vole habitat. The report concludes that no evidence of any water voles were found within the study area. A Reptile Survey Report, dated June 2019, has been submitted, which concludes that common lizards were recorded at relatively low-moderate density in the survey area between the period 13/05/2019 to 18/06/2019. No other reptile species were recorded. A species protection plan is therefore recommended within the report to provide mitigation measures for reptiles.
c) Arboricultural information including: Tree Schedule, tree survey report, arboricultural impact assessment and method statement: an initial tree survey report was provided with the original submission details together with a tree schedule confirming the scope of works, survey methodology and survey results of the existing trees on site. The trees surveyed consisted of self-sown alder, willow and birch in the eastern site corner, with a low quality recorded for the cluster, although good quality birch were recorded. A total of 32 trees were surveyed. A further report was submitted in support of the application detailing the arboricultural impact assessment and method statement for the site. The report recommends that a total of 8 category C trees and three category U trees are to be removed which is detailed as having a minimal to moderate effect on the landscape. The report also details the tree protection measures to be implemented for the retained trees on site together with compensatory planting and landscaping scheme.
d) Revised drainage impact assessment: the revised document confirms that foul water from the development will drain via a proposed foul pump station (to be adopted by Scottish Water) and private connections will be made to this from each unit to a new gravity sewer within the access roads. Regarding surface water, roof water is proposed to be drained to the proposed surface water sewer which will then discharge to a detention basin. Private shared car parking areas is proposed to drain via porous block paving to underlying sub-base which will be surrounded in a layer of geotextile, with a controlled discharge to the boundary ditch. The adoptable road area is proposed to drain via road gullies conveying to a detention basin. It is proposed that Highland Council Roads Department will adopt the gully connections whilst Scottish Water will adopt the remainder of the drainage system including the detention basin. The detention
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
basin has been designed to manage surface water flow generated by the development up to and including a I in 200 year storm event and additional 30% climate change and 10% urban creep allowances. The existing open ditch is proposed as a boundary filter trench which has been designed to have at least the same hydraulic capacity as existing. The report concludes that a sustainable drainage solution for the proposal can be implemented. The appendices include the ground investigation reports, drainage calculations, layouts and assessment for the relocated ditch.
e) Drainage and flood assessments including: storm and flood calculations, SUDS basin impermeable areas calculations, post development run off calculations and Suds Basin calculations: further flood and run off calculations have been provided by the agent to demonstrate the discharge levels from the site drainage in regards to limiting it to the pre- development greenfield rate for the corresponding return period storm events.
f) Boundary ditch maintenance schedule: outlines the maintenance of the existing boundary ditch within the site during the construction period and post construction. It confirms that maintenance access has been retained to the ditch with a minimum Imetre maintenance strip to provide retained between the ditch and proposed garden fences. The ditch is proposed to be inspected on an annual basis.
g) Ground maintenance schedule: a five year maintenance schedule for the soft landscaping works of the scheme has been submitted, which includes details such as the replacement of any plant deaths after the first year of planting during the five year period and notes that the maintenance will firstly be undertaken by the landscape contractor and then it will revert to the Factor (Highland Housing Alliance and Highland Council).
Plans of the proposal are included within Appendix I.
At the time of submission of the application the applicants were Bespoke Highland Homes. The application site is now under the control of Highland Housing Alliance who are now the applicants with revised application forms submitted and they wish the application to proceed to a conclusion.
History
- The site has an extant planning permission under Highland Council application reference: 04/00118/FULBS for the ‘formation of access road and sewage pumping station and subdivision of land to form 10 house plots’ which was submitted in April
- Permission was granted on 29 June 2010 and works originally began on the installation of the road access bellmouth.
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
DEVELOPMENT PLAN CONTEXT
Policies
National Policy | Scottish Planning Policy 2014 | |
---|---|---|
Strategic Policy | Cairngorms National Park Partnership Plan 2017 — 2022 | |
Local Plan Policy | Cairngorms National Park Local Development Plan (2015) | |
Those policies relevant to the assessment of this application | ||
are marked with a cross | ||
POLICY I | NEW HOUSING DEVELOPMENT | X |
POLICY 2 | SUPPORTING ECONOMIC GROWTH | |
POLICY 3 | SUSTAINABLE DESIGN | X |
POLICY 4 | NATURAL HERITAGE | X |
POLICY 5 | LANDSCAPE | X |
POLICY 6 | THE SITING AND DESIGN OF DIGITAL COMMUNICATIONS EQUIPMENT | |
POLICY 7 | RENEWABLE ENERGY | |
POLICY 8 | SPORT AND RECREATION | |
POLICY 9 | CULTURAL HERITAGE | |
POLICY 10 | RESOURCES | X |
POLICY 11 | DEVELOPER CONTRIBUTIONS | X |
All new development proposals require to be assessed in relation to policies contained in the adopted Local Development Plan. The full wording of policies can be found at: http://cairngorms.co.uk/uploads/documents/Park Authority/Planning/LDP15.pdf
The site is identified within the Dulnain settlement statement of the Cairngorms Local Development Plan 2015 for housing development under the designation EP1 – Adjacent to A938 where it is stated as follows: identified as existing consent for 10 units.
Planning Guidance
- Supplementary guidance also forms part of the Local Development Plan and provides more details about how to comply with the policies. Guidance that is relevant to this application is marked with a cross.
Policy I | New Housing Development Non-Statutory Guidance | X |
---|---|---|
Policy 2 | Supporting Economic Growth Non-Statutory Guidance | |
Policy 3 | Sustainable Design Non-Statutory Guidance | X |
Policy 4 | Natural Heritage Supplementary Guidance | X |
Policy 5 | Landscape Non-Statutory Guidance | X |
Policy 7 | Renewable Energy Supplementary Guidance | |
Policy 8 | Sport and Recreation Non-Statutory Guidance | |
Policy 9 | Cultural Heritage Non-Statutory Guidance | |
Policy 10 | Resources Non-Statutory Guidance | X |
Policy 11 | Developer Contributions Supplementary Guidance | X |
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
Cairngorms National Park Local Development Plan 2020
The emerging Cairngorms National Park Local Development Plan (“Proposed Plan”) which will cover the period 2020 – 2025 is currently being progressed. The proposed plan has been through a public consultation process and the formal responses have been assessed and submitted along with all other relevant materials to Scottish Ministers for examination. As the examination of the Proposed Plan is yet to start, the Proposed Plan and its contents currently carry limited weight. In addition, proposals and policies which received heavy objection following the public consultation process are afforded even less weight.
Within the Proposed Plan, Dulnain H2 site remains allocated for housing and the 1.3ha site has an indicative residential capacity of 20 units. The Plan states “the site currently benefits from an existing permission for 10 dwellings, however there are opportunities to increase the number of units to 20.” Following the public consultation on the proposed plan, no objections were received to the proposed H2 Housing allocation at Dulnain Bridge.
CONSULTATIONS
Summary of the main issues raised by Consultees
Scottish Environment Protection Agency (SEPA) has no objection to the application on flood risk grounds and refer to the local authority Flood Team for their comments regarding surface water drainage issues and mitigation measures.
Scottish Water were consulted on the application but have not provided any formal response regarding the scheme.
Highland Council Transport Planning Team has provided four consultation responses throughout the progression of this application. The Transport Planning Team raised objection during their first and second responses and required the submission of further information to inform the analysis of the development. Their comments on the latest scheme have been summarised under the following headings below:
a) Access from A938: The Transport Planning Team confirm that they have no objection to a visibility splay x distance of 2.4 metres being applied as the proposed development is relatively small and will not generate significant levels of new traffic.
b) Site layout: The Transport Planning Team still require the submission of a plan demonstrating the forward visibility splay of plot 15 as required on road safety grounds.
c) Conditions summary: The Team request planning conditions are attached to any consent given for the footway to be installed prior to any occupation of any dwelling; the extension of the 30mph zone to be implemented prior to the commencement of any construction works and the requirement for a SUDS scheme along the A938 adjacent to the development site to be agreed and implemented.
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
Following the applicant’s revision of the plans to show the forward visibility splay of plot 15, the Highland Council Transport Planning Team accept the proposed reduced forward visibility splay at the bend, given the provision of traffic calming measures within the scheme. They note that the landscaping drawing would need to be amended to move the Rowan tree further away from the splay.
Highland Council Housing Service confirms that, in their opinion, the development provides for much needed family housing in Badenoch and Strathspey and the Housing Service therefore has no comments or objections to the plans as they stand.
Highland Council Flood Risk Management Team has considered the submission details (July 2019) of the application and maintained their original objection to the proposal. Regarding drainage matters, the Team object as the cut-off ditch is proposed to be located within private property boundaries with no maintenance access or defined maintenance responsibilities. They also require the demonstration that the discharge from the site drainage is limited to the pre-development greenfield rate for the corresponding return period storm events.
Following the submission of revised information on 19 August 2019, the Flood Risk Management Team confirm that they withdraw their previous objection to the application noting that the site layout has been modified and the ditch at the rear of the site is not within any of the plot boundaries. Maintenance access would be retained to the ditch and the drainage calculations provided demonstrate that surface water discharge from the site will be attenuated to the pre-development greenfield rates for storms up to and including the I in 200 year plus climate change event.
Highland Council Forestry Officer has provided comments on the March 2019 revisions. The Officer has no objection to the principle of the development but objected to the application at that stage due to the following concerns:
a) The Officer noted that the tree schedule had not been updated and tree constraints plan have not been revised as part of the submission. The Officer queries the tree quality assessment and notes that the tree schedule records almost all of the trees as having an estimated remaining contribution of greater than 20 years.
b) The Officer considers the reduction of trees to be removed is an improvement as it now allows for the retention of 21 trees on site. Regarding the tree protection plan, the Officer requires a condition to be attached to any subsequent decision for the provision of protection measures to some of the adjacent trees outwith the site boundary.
c) The Officer requires the submission of a more robust landscape plan incorporating planting at the west end of the site and between the houses and road to provide further compensation for tree losses and to add positively to the character and setting of the development.
- Following the revisions to the latest scheme (documents submitted in July 2019), the Officer confirms that the tree protection measures and the landscape plan are generally acceptable but requests the addition of post determination conditions
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
seeking refinements to the landscape plan and the Aboricultural Method Statement and relating to the tree protection measures to be maintained on site.
Highland Council Contaminated Land Officer having checked their historical records confirms that there are no known issues in terms of potential contaminated land at the site and the Contaminated Land Service therefore has no comment on the scheme.
Highland Council Environmental Health Officer were consulted on the application but have not provided any formal response regarding the scheme.
CNPA Landscape Officer originally advised that the development would have minimal impact upon the landscape character of the site, as the current land is of natural value. For the wider landscape character it was advised that the proposal, subject to design, should seek to avoid introducing hard edges to the development following a principle of seamless linkages of the housing and garden grounds into the surrounding landscape.
In terms of landscape and visual character, the Landscape Officer advised that a high quality design in terms of layout, orientation, form, scale and materials should be sought which enhanced the experience of entering the village form the west along the A938. Concerns were previously raised by the Officer at pre-application stage over the design and in particular concern of the rear view fronting on the principle route in Dulnain Bridge. The Officer raised a number of concerns with the original scheme as submitted which include: an inward looking development which would not be integrated as part of the village townscape and is contrary to the predominant built character of this part of the settlement; a lack of detail to be able to make a judgement on the degree of screening the planting proposed would provide; a lack of detail on the proposed tree planting and vegetation planting; insufficient information regarding the tree survey and tree plan; and insufficient information of how the proposed SUDs will be integrated into the landscape.
Following the March 2019 revisions, the Landscape Officer reiterated that the fundamental design of the proposal remained unchanged from the original submission and therefore the development remained contrary to the prevailing townscape character of Dulnain Bridge and disconnected. The sense of disconnection was considered by the Officer to be emphasised further by the boundary treatment along the publicly visible flanks of the scheme where the landscaping proposed was considered to be at a poor quality. The Officer concluded that the development does not take account of the opportunities the site provides and the conclusions reached in the original consultation response still stand. The Officer provided the following additional comments at this stage of the application progression:
a) Tree Planting: The Officer notes that the details of the revised landscaping scheme suggest standard planting with 8 new trees located where land is not developable and not in response to the context of the landscape.
b) Fencing: The Officer notes that clarity has been provided on the boundary treatments, however the proposed fencing adds to the introverted nature of the development.
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Item 6 11/10/2019
c) Tree Protection Plan: The additional plan provides greater clarity on the location of the trees affected and enable cross referencing with the already submitted Tree Survey.
d) SUDS design: The Officer notes that the details maintained an engineered SUDs design with an access road encircling the basin and further encircled by stock fencing.
- On considering the latest details, the Landscape Officer has provided comment on how the proposal looks to address five key landscape considerations previously raised through the consultation process. These are as follows:
a) Poor planting plan and lack of cover on southern and western sides of the site: The planting plan has been improved although could be improved further by using a natural flower and grassland seed mix throughout the site to provide a more coherent planting scheme by tying together the visually isolated groups of shrub and a revised management plan would therefore be required which could be dealt with by way of planning condition. The Officer also suggests minor amendments to the proposed shrub mix including double planting to ensure a good planting scheme is established.
b) Inadequate tree planting and protection plan: the additional tree planting proposed is considered acceptable by the Officer however, reference is made to comments from the Highland Council Forestry Officer.
c) Fencing dominates and creates introverted character of the site: The Officer considers that a more simplistic fence line would be appropriate in this area and suggests use of a 1.4 metre fence with high points added by trees planted and a change in height before the frontage fence should occur I metre or so before to ensure a more attractive junction.
d) SUDS: the Officer advises that the interior of the SUDs basin should be sown with a wild flower and grass land mix to provide visual interest and biodiversity benefit.
e) Contrary to village character and does little to address the key site at entrance to the village: the overall plan has not changed significantly and therefore the Officers previous comments are still of relevance.
The Officer notes that should approval be recommended then the landscape measures mentioned above can all be conditioned.
CNPA Ecology Officer has reviewed the supporting documentation and provided comments on each of the scheme’s revisions. The Officer references