Cairngorms Nation­al Park Author­ity Intern­al Audit Pro­gress Report — Novem­ber 2020

AV AZETS

CAIRNGORMS NATION­AL PARK AUTHORITY Audit & Risk Com­mit­tee Paper 3 27/11/2020

Sum­mary

This paper provides the Audit and Risk Com­mit­tee with a sum­mary of intern­al audit activ­ity since its last meet­ing and con­firms the reviews planned for the com­ing quarter, identi­fy­ing any changes to the annu­al plan.

We were due to present the VAT Health Check report, Out­door Access Infra­struc­ture report and Fol­low Up Part 1 report to the Novem­ber meet­ing; how­ever, field­work remains ongo­ing on the VAT Health Check review, and we are cur­rently in dis­cus­sions with man­age­ment on obtain­ing the inform­a­tion for the Out­door Access Infra­struc­ture and Fol­low Up reviews. As such, these reports will now be presen­ted to the March meet­ing. In addi­tion, man­age­ment have reques­ted that the ICT Strategy review be deferred to the 202122 Intern­al Audit Plan.

Status of intern­al audit reviews 202021 (Pie chart show­ing dis­tri­bu­tion of Com­plete, Field­work in pro­gress, Planned, Plan­ning, Deferred)

Plan for next quarter

The fol­low­ing reports are due to be presen­ted to the March 21 Audit and Risk Committee:

  • VAT Health Check
  • Cor­por­ate Governance
  • Cov­id Recovery
  • Leg­acy Liabilities
  • Out­door Access Infrastructure
  • Data Man­age­ment
  • Fol­low Up
  • 202021 Annu­al Intern­al Audit Report
  • 202122 Intern­al Audit Plan

Action for Committee

The Audit and Risk Com­mit­tee is asked to note the con­tents of this report and to approve the plan for the next quarter. We also invite any com­ments on the format or con­tent of this report.

Chris Brown, Audit Part­ner [email protected] 0131 473 3500 Stephanie Hume, Audit Man­ager [email protected] 01463 704 866

202021 audit plan progress

Ref and Name of reportQuarterCur­rent statusPlanned ACCActu­al ACC
A4. VAT Health CheckQ2Field­work in ProgressMar 21
B1. Cor­por­ate GovernanceQ2PlannedMar 21
C1. Cov­id RecoveryQ2Field­work in ProgressMar 21
C2. Leg­acy LiabilitiesQ3Plan­ningMar 21
C3. Out­door Access InfrastructureQ2Plan­ningMar 21
D1. ICT StrategyDeferredN/AN/A
D4. Data ManagementQ3Plan­ningMar 21
E1. LEAD­ER AdministrationQ1Com­pleteSept 20Sept 20
E2. Fol­low UpQ3Plan­ningMar 21
Annu­al reportN/AMar 21

Key:

StatusDescrip­tion
Com­pleteAudit work com­plete and report has been agreed and finalised
Draft ReportA draft report has been issued
Field­work completeThe audit work is com­plete but the draft report has not yet been issued.
Field­work in progressThe audit work is in progress.
PlannedThe scope and tim­ing of the audit has been agreed with management
Plan­ningThe scope and/​or tim­ing of the audit has yet to be agreed with management

© Azets 2020. All rights reserved. Azets refers to Azets Audit Ser­vices Lim­ited. Registered in Eng­land & Wales. Registered No. 09652677. VAT Regis­tra­tion No. 219 0608 22.

Registered to carry on audit work in the UK and reg­u­lated for a range of invest­ment busi­ness activ­it­ies by the Insti­tute of Chartered Account­ants in Eng­land and Wales.

×