201127AuCtteePaper3AAProgress Report Nov 2020Azets
Cairngorms National Park Authority Internal Audit Progress Report — November 2020
AV AZETS
CAIRNGORMS NATIONAL PARK AUTHORITY Audit & Risk Committee Paper 3 27/11/2020
Summary
This paper provides the Audit and Risk Committee with a summary of internal audit activity since its last meeting and confirms the reviews planned for the coming quarter, identifying any changes to the annual plan.
We were due to present the VAT Health Check report, Outdoor Access Infrastructure report and Follow Up Part 1 report to the November meeting; however, fieldwork remains ongoing on the VAT Health Check review, and we are currently in discussions with management on obtaining the information for the Outdoor Access Infrastructure and Follow Up reviews. As such, these reports will now be presented to the March meeting. In addition, management have requested that the ICT Strategy review be deferred to the 2021⁄22 Internal Audit Plan.
Status of internal audit reviews 2020⁄21 (Pie chart showing distribution of Complete, Fieldwork in progress, Planned, Planning, Deferred)
Plan for next quarter
The following reports are due to be presented to the March 21 Audit and Risk Committee:
- VAT Health Check
- Corporate Governance
- Covid Recovery
- Legacy Liabilities
- Outdoor Access Infrastructure
- Data Management
- Follow Up
- 2020⁄21 Annual Internal Audit Report
- 2021⁄22 Internal Audit Plan
Action for Committee
The Audit and Risk Committee is asked to note the contents of this report and to approve the plan for the next quarter. We also invite any comments on the format or content of this report.
Chris Brown, Audit Partner [email protected]
0131 473 3500 Stephanie Hume, Audit Manager [email protected]
01463 704 866
2020⁄21 audit plan progress
Ref and Name of report | Quarter | Current status | Planned ACC | Actual ACC |
---|---|---|---|---|
A4. VAT Health Check | Q2 | Fieldwork in Progress | Mar 21 | |
B1. Corporate Governance | Q2 | Planned | Mar 21 | |
C1. Covid Recovery | Q2 | Fieldwork in Progress | Mar 21 | |
C2. Legacy Liabilities | Q3 | Planning | Mar 21 | |
C3. Outdoor Access Infrastructure | Q2 | Planning | Mar 21 | |
D1. ICT Strategy | Deferred | N/A | N/A | |
D4. Data Management | Q3 | Planning | Mar 21 | |
E1. LEADER Administration | Q1 | Complete | Sept 20 | Sept 20 |
E2. Follow Up | Q3 | Planning | Mar 21 | |
Annual report | N/A | Mar 21 |
Key:
Status | Description |
---|---|
Complete | Audit work complete and report has been agreed and finalised |
Draft Report | A draft report has been issued |
Fieldwork complete | The audit work is complete but the draft report has not yet been issued. |
Fieldwork in progress | The audit work is in progress. |
Planned | The scope and timing of the audit has been agreed with management |
Planning | The scope and/or timing of the audit has yet to be agreed with management |
© Azets 2020. All rights reserved. Azets refers to Azets Audit Services Limited. Registered in England & Wales. Registered No. 09652677. VAT Registration No. 219 0608 22.
Registered to carry on audit work in the UK and regulated for a range of investment business activities by the Institute of Chartered Accountants in England and Wales.