220211AuCtteePaper6Annex1StrategicRiskRegister

CAIRNGORMS NATION­AL PARK AUTHOR­ITY STRA­TEGIC RISK REGISTER

Audit and Risk Com­mit­tee Paper 6 Annex 1 11/02/22

RiskRefRespMit­ig­a­tionCom­mentsTrend June 21Trend Sep 21Trend Jan 22
Cross-over risks
Resources: pub­lic sec­tor fin­ances con­strain capa­city to alloc­ate suf­fi­cient resources to deliv­er cor­por­ate plan.A1DCPre­vent­at­ive: Ongo­ing liais­on with Scot­tish Gov­ern­ment high­light­ing achieve­ments of CNPA. Pre­vent­at­ive: Cor­por­ate plan pri­or­it­ised around anti­cip­ated Scot­tish Gov­ern­ment budget alloc­a­tions, tak­ing on Board expect­a­tion of fund­ing con­straints. Remedi­al: Focus resource on diver­si­fic­a­tion of income streams to altern­ate, non-pub­lic income gen­er­a­tion. Remedi­al: Con­tinu­ing to sup­port deliv­ery bod­ies” such as Cairngorms Nature, Cairngorms Trust in secur­ing inward investment.Now near­ing end of cur­rent Cor­por­ate Plan peri­od there­fore this risk spe­cific­ally about resourcing to March 22 man­aged to suc­cess­ful out­come. Cor­por­ate Plan out­comes may be exten­ded bey­ond March 22 as part of agreed trans­ition­al cor­por­ate plan­ning pro­cess. While Board has still to con­sider budget and alloc­a­tions for 202223, the alloc­a­tions from Scot­tish Gov­ern­ment appear in line with expect­a­tions and requirements.⬇️⬇️⬇️
Resourcing / Staff­ing / Policy: exten­ded impacts of COVID19 to organ­isa­tion impacts core stra­tegic object­ives and requires early stra­tegic plan review.A23DCRemedi­al: sep­ar­ate COVID19 oper­a­tions risk register estab­lished to help identi­fy and mit­ig­ate spe­cif­ic risks. Remedi­al: altered, widened man­age­ment meet­ings to include all Heads of Ser­vice thus ensur­ing close mon­it­or­ing of stra­tegic impactsMan­age­ment of spe­cif­ic COV­ID stra­tegic and oper­a­tion­al risks are set out in the sep­ar­ate risk register doc­u­ment. Evid­ence over last peri­ods of COV­ID mit­ig­a­tion being effect­ive and focus remain­ing on stra­tegic objectives.⬇️⬇️⬇️
Resourcing: future com­munity led loc­al devel­op­ment fund­ing cur­rently delivered through LEAD­ER, togeth­er with wider fund­ing pre­vi­ously from EU struc­tur­al and agri­cul­tur­al sources is lost and cre­ates a sig­ni­fic­ant gap in our capa­city to deliv­er against our devel­op­ment prioritiesA12.2DCPre­vent­at­ive: pri­or­it­ise engage­ment in con­sulta­tions and events around the future devel­op­ment of struc­tur­al and com­munity fund­ing. Remedi­al: con­tin­ue to sup­port work of Cairngorms Trust in attract­ing vol­un­tary dona­tions toward com­munity action – although this is likely to remain at a much smal­ler scale for some time. Remedi­al: con­tin­ue to review oppor­tun­it­ies for fund­ing bids to oth­er non-gov­ern­ment­al fund­ing sources.Pos­it­ive move­ment across policy devel­op­ment areas with­in Scot­tish Gov­ern­ment around the con­tinu­ity of some form of CLLD. How­ever, timetable for any devel­op­ment pro­cess still very unclear, as is poten­tial of UK Gov­ern­ment fund­ing to replace EU losses. Wider changes to agri-envir­on­ment schemes and impact of change also remains highly uncertain.⬆️⬆️⬆️
Staff­ing: addi­tion­al extern­ally fun­ded pro­jects strains staff work­load capa­city with increased risks of stress and reduced morale.A9.3DCPre­vent­at­ive: Stra­tegic and oper­a­tion­al plans for 202223 will be developed with extern­ally fun­ded pro­ject deliv­ery as intrins­ic ele­ments of plans to ensure deliv­ery capa­city is con­sidered fully. Import­ance of staff man­age­ment and task pri­or­it­isa­tion rein­forced through lead­er­ship meet­ings. Focus on few­er, lar­ger impact projects.Risk escal­a­tion in recog­ni­tion of suc­cess in sig­ni­fic­ant Her­it­age Hori­zons award and early stages of plan­ning resource deploy­ment around that step-change in activ­ity level.➡️⬆️⬆️
Resourcing: Role as Lead / Account­able body for major pro­grammes (e.g. LEAD­ER, Land­scape Part­ner­ship) has risk of sig­ni­fic­ant fin­an­cial claw­back should expendit­ure prove to be not eli­gible for fund­ing, while CNPA car­ries respons­ib­il­it­ies as employ­er for pro­gramme staff.A11.1DCPre­vent­at­ive: Ensure fin­an­cial con­trols in place for pro­gramme man­age­ment include effect­ive eli­gib­il­ity checks. Test pro­cesses with fun­ders if required and also under­take early intern­al audit checks. Work­force man­age­ment plans must incor­por­ate pro­gramme staff con­sid­er­a­tions. Ensure TGLP Man­age­ment and Main­ten­ance con­tracts are all in place to ensure eli­gib­il­ity of invest­ment. Remedi­al: Util­ise intern­al audit resourcesLEAD­ER Pro­jects have been brought to a close by the 31 Decem­ber 21 dead­line with the final admin claim to be made by end Janu­ary. To date, no clos­ure issues have aris­en and good work in part­ner­ship with the cur­rent cent­ral team in Edin­burgh to recon­cile and final­ise pos­i­tions. Work has pro­gressed well on clos­ure of Tomin­toul and Glen­liv­et and on Badenoch pro­grammes with no issues arising to date.⬇️⬇️⬇️
Resourcing: the end of major pro­gramme invest­ments (Tomin­toul and Glen­liv­et, LEAD­ER) requires sig­ni­fic­ant ongo­ing staff­ing to man­age audit and leg­acy which the Author­ity finds dif­fi­cult to resource.A11.2DCPre­vent­at­ive: Early iden­ti­fic­a­tion of post-pro­gramme audit and leg­acy man­age­ment and resourcing require­ments and plan­ning for those. Early engage­ment with Cairngorms Trust for LEAD­ER and Land­scape Part­ner­ship Pro­gramme Board to identi­fy and final­ise long term man­age­ment arrangements.Added by Man­age­ment Team Novem­ber 2019 To date, leg­acy issues appear man­age­able, and plans now in place to pro­tect some staff resource over 202223 to cov­er any ongo­ing LEAD­ER clos­ure and leg­acy work.⬇️⬇️⬇️
Tech­nic­al: Increas­ing ICT depend­ency for effect­ive and effi­cient oper­a­tions is not adequately backed up by ICT sys­tems support.A17DCPre­vent­at­ive: invest in addi­tion­al staff resource. Deploy timetabled action plan against approved ICT Strategy Remedi­al: New ICT Strategy to be developed to reappraise pos­i­tion on IT depend­en­cies and estab­lish a focus for future digit­al devel­op­ment across the Author­ity. Clear action plan­ning to evolve from final ICT stra­tegic dir­ec­tion once agreed.Added April 2018 Oper­a­tion­al Scale of for­ward ICT invest­ment to sup­port infra­struc­ture devel­op­ment work and organ­isa­tion­al devel­op­ment plans as we move to a post-COV­ID new nor­mal” sig­ni­fies sig­ni­fic­ant work­load and sup­port require­ments. ICT Strategy in place; added staff recruit­ment suc­cess­fully com­pleted. Timetabled action plan in development.⬆️⬆️➡️
Tech­nic­al: Cyber secur­ity is inad­equate to address risk of cyber-attack on systemsA18DCPre­vent­at­ive: Imple­ment­a­tion of Scot­tish Gov­ern­ment Cyber Secur­ity Action Plans and intern­al audit recom­mend­a­tions on IT secur­ity. Ongo­ing review of sys­tems and pro­ced­ures in tan­dem with LLT­NPA. Rescope arrange­ments through IT Strategy. Invest in cyber secur­ity softwareAdded by MT / OMG April 18. Cyber secur­ity plus accred­it­a­tion received. Addi­tion­al cyber secur­ity meas­ures inves­ted in and imple­men­ted. Aware of increased risks high­lighted by nation­al agen­cies dur­ing COV­ID response. Invest­ment in cyber secur­ity soft­ware completed⬇️➡️➡️
Resourcing: CNPA IT ser­vices are not suf­fi­ciently robust / secure / or well enough spe­cified to sup­port effect­ive and effi­cient ser­vice delivery.A13DCPre­vent­at­ive: We will devel­op and con­sult on the for­ward plans for ICT ser­vice devel­op­ment to ensure these meet ser­vice require­ments. Com­mis­sioned extern­al review of our IT and data man­age­ment pro­cesses to be imple­men­ted to give assurance.Risk added through staff con­sulta­tion with Staff Con­sultat­ive For­um Sep 2016. Actions imple­men­ted on Cyber Secur­ity. Very high levels of ser­vice avail­ab­il­ity. It ser­vices have con­tin­ued to sup­port remote work­ing over COV­ID BCP peri­od. Size of team increased to resource work required to design and imple­ment the ser­vice changes sup­port­ing hybrid operations.⬆️⬆️➡️
Repu­ta­tion: One-off, high pro­file incid­ents and / or voci­fer­ous social media cor­res­pond­ents have an undue influ­ence on the Authority’s pos­it­ive reputation.A14.1GMPre­vent­at­ive: Engage­ment and com­mu­nic­a­tions strategy, and stake­hold­er engage­ment will seek to take the front foot on man­aging the Authority’s pos­it­ive, pub­lic repu­ta­tion Pre­vent­at­ive: pro­act­ive com­mu­nic­a­tions ini­ti­ated to address any poten­tial incid­ents Remedi­al: involve­ment in emer­ging NPUK col­lect­ive com­mu­nic­a­tions strategy and cam­paigns which will pro­duce addi­tion­al high pro­file pos­it­ive repu­ta­tion­al impact Remedi­al: Social media pro­file rep­res­ents an oppor­tun­ity to boost reputation.Adop­ted by ARC Novem­ber 20 to con­sol­id­ate all repu­ta­tion­al risks. Recruit­ment now com­plete to sup­port this work with­in the com­mu­nic­a­tions team. While incid­ents and neg­at­ive social media inter­ac­tions occur from time to time, over­all sense of cur­rent pos­i­tion is a decline in this risk area.➡️➡️⬇️
Resourcing: scale of asset respons­ib­il­it­ies such as for paths, out­door infra­struc­ture is not adequately recog­nised and does not secure adequate for­ward main­ten­ance funding.A16DCRemedi­al: Review of account­ing pro­ced­ures and asset recog­ni­tion policy; review of forth­com­ing account­ing tech­nic­al guid­ance. Ensure full con­sid­er­a­tion is giv­en in budget reviews. Pre­vent­at­ive: Cap­it­al bids to gov­ern­ment; altern­ate fund­ing sources such as vol­un­tary giv­ing to be explored more act­ively. Work on Stra­tegic Tour­ism Vis­it­or Infra­struc­ture Plan to focus action.Added by MT / OMG April 18. Infra­struc­ture main­ten­ance issues exacer­bated by end of exist­ing agree­ments over key routes and by addi­tion­al COV­ID 19 related vis­it­or pres­sures, while COV­ID has also dis­rup­ted plans around imple­ment­a­tion of vol­un­tary giv­ing schemes. Sig­ni­fic­ant increase in cap­it­al alloc­a­tion allows scope for increased pro­gram­ming of main­ten­ance over next four to five year period.➡️➡️➡️
Resourcing: change in fin­an­cing IT ser­vices and the switch from cap­it­al to rev­en­ue pro­vi­sion places an unman­age­able pres­sure on the Authority’s budget capacity.A20DCRemedi­al: Mon­it­or pat­tern of IT invest­ment costs as regards the cap­it­al and rev­en­ue split of resourcing require­ments; build impacts into ongo­ing budget delib­er­a­tions with Scot­tish Government.Added by Audit Com­mit­tee 8 March 2019 fol­low­ing deep dive” IT risk review. Risk remains live as we imple­ment a refreshed ICT Strategy and move to more cloud / ser­vice solutions➡️➡️➡️
Repu­ta­tion: the Author­ity is not per­ceived to be appro­pri­ately address­ing the poten­tial for con­flict between 4 stat­utory aims.A21GMPre­vent­at­ive: Ensure Board policy papers and Plan­ning Com­mit­tee papers are expli­cit in recog­nising stra­tegic policy con­flicts between 4 stat­utory aims and in address­ing the eval­u­ation of any poten­tial con­flict. Pre­vent­at­ive: ensure clar­ity on this mat­ter is estab­lished through high level NPPP and Cor­por­ate Plan documentsAdded by Audit Com­mit­tee 8 March 2019 fol­low­ing intern­al audit report on stra­tegic plan­ning pro­cesses. NPPP devel­op­ment pro­cess now under­way where this can start to be underpinned.➡️➡️➡️
Tech­nic­al: Busi­ness Con­tinu­ity Plans (BCP) are inad­equate to deal with sig­ni­fic­ant impacts to nor­mal work­ing arrange­ments and res­ult in ser­vice failure.A22DCPre­vent­at­ive: Over­haul of BCP developed in 2014 with report­ing on devel­op­ment of plans through Man­age­ment Team and Audit and Risk Com­mit­tee. Test BCP arrange­ments once plan in place and com­mu­nic­ated. Remedi­al: intern­al audit review of COVID19 over winter 2021 will lead into les­sons learned on wider BCP.Added by Audit Com­mit­tee May 2019 fol­low­ing intern­al audit review of BCP. Some delay in final­isa­tion of BCP doc­u­ment­a­tion itself. How­ever, work on BCP has con­sid­er­ably assisted in roll out of ini­tial and ongo­ing responses to Coronavir­us pan­dem­ic with evid­ence, includ­ing very pos­it­ive staff feed­back, that BCP imple­ment­a­tion has been effective.➡️➡️➡️
Tech­nic­al: the Authority’s range of powers com­bined with stra­tegic part­ner­ships is insuf­fi­cient to deliv­er out­comes on wild­life crimeA24AFRemedi­al: use NPPP devel­op­ment pro­cesses to explore part­ner­ship atti­tudes, engage­ment and powers which they may add to the cur­rent con­trols. Pre­vent­at­ive: explore poten­tial for licen­cing or oth­er reg­u­lat­ory arrange­ments to con­trib­ute to more effect­ive con­trol frameworkAdded by SMT risk review May 2021 Mit­ig­a­tion actions still in form­at­ive stages and risk pro­file retained.⬆️⬆️⬆️
Tech­nic­al: The Authority’s Peat­land Pro­gramme out­comes may be adversely impacted by a lack of con­tract­or capacityA25MFPre­vent­at­ive: inter­ac­tion with skills and eco­nom­ic devel­op­ment agen­cies to high­light the prob­lems of con­tract­or capa­city and scale of future programmeAdded by SMT risk review May 2021 Recent fail­ure to pro­cure tenders for con­tract con­firms risk. Pos­it­ive sig­nals around the effect­ive­ness of team in work­ing with the con­tract­or sup­ply side of the sec­tor with optim­ism that situ­ation may improve as we move into peri­od to tender for works over 202223. Risk pro­file retained pending evid­ence of con­tract­or responses to tenders in 2022.⬆️⬆️⬆️
Repu­ta­tion­al: key com­mu­nic­a­tions activ­it­ies, mes­saging and (in some cases) brand aware­ness rais­ing can be depend­ent on part­ner col­lab­or­a­tion rather than under dir­ect con­trol, with poten­tial for inef­fect­ive or dis­join­ted com­mu­nic­a­tion outcomes.A26GMPre­vent­at­ive: agree part­ner­ship frame­works that expli­citly set out expect­a­tions and out­comes of col­lab­or­at­ive activ­it­ies and estab­lish adequate con­trol mech­an­isms; Pre­vent­at­ive: spe­cific­ally mon­it­or and feed­back on com­mu­nic­a­tions effect­ive­ness where there are part­ner­ship depend­en­cies Remedi­al: con­duct review meet­ings which track and doc­u­ment pro­gress and escal­ate and issues arising to appro­pri­ate gov­ernance groups.Added by SMT risk review May 2021. Iden­ti­fied as a stable risk at present rather than escal­at­ing, while recog­nised that work remains to be under­taken around these pre­vent­at­ive and remedi­al mit­ig­a­tion measures.➡️➡️➡️
Tech­nic­al: approaches to con­ser­va­tion and pro­tec­tion of endangered spe­cies may be insuf­fi­cient to achieve asso­ci­ated stra­tegic outcomesA27AFRemedi­al: review cur­rent approaches in con­text of rel­ev­ant data sources to determ­ine adequacy of cur­rent approaches. Remedi­al: use NPPP devel­op­ment pro­cesses to test poten­tial for enhanced / revised approaches to con­ser­va­tion and pro­tec­tion of endangered speciesAdded by SMT risk review May 2021. Iden­ti­fied as a stable risk at present rather than escal­at­ing, while recog­nised that work remains to be under­taken or is ongo­ing around these pre­vent­at­ive and remedi­al mit­ig­a­tion measures.➡️➡️➡️
Staff­ing: deliv­ery of key out­comes is impacted by staff turnover, par­tic­u­larly in pro­ject teams.A28DCPre­vent­at­ive: con­sider HR solu­tions to encour­age reten­tion Remedi­al: ensure suc­ces­sion plan­ning and oper­a­tion­al risk registers cov­er this stra­tegic riskAdded fol­low­ing Board reflec­tion on impact of turnover in TGLP Project.
Staff­ing: increas­ingly com­pet­it­ive and restric­ted recruit­ment cli­mate pre­vents staff with the required exper­i­ence and skill sets being securedA29DCPre­vent­at­ive: focus on train­ing and devel­op­ment and intern­al suc­ces­sion plan­ning, in turn bring­ing recruit­ment into less exper­i­enced / less highly skilled mar­kets; con­sider job design and flex­ib­il­ity of offer regard­ing part-time / job share. Remedi­al: con­tin­gency plan­ning for example around out-sourcing of aspects of delivery.Added by SMT review 18 Jan. Evid­ence of redu­cing num­ber of applic­ants and can­did­ate lists for vacan­cies and emer­ging trend in unsuc­cess­ful recruit­ment exercises.➡️

Notes:

  • Aim­ing to keep stra­tegic risk register to around 15 stra­tegic risks
  • Cross-cut­ting risks impact poten­tially through­out all priorities
  • Stra­tegic Risks around cor­por­ate pri­or­it­ies focus on risk impacts through­out each of the three themes – hence require a coordin­ated over­view at Dir­ect­or / Exec­ut­ive level. Not expect­ing a stra­tegic risk against each spe­cif­ic Cor­por­ate Plan priority.
  • More spe­cif­ic risks are expec­ted to be cap­tured in more oper­a­tion­al risk registers – e.g. risk man­age­ment around deliv­ery of office extension.
  • Full risk register the col­lect­ive respons­ib­il­ity of full MT to man­age, how­ever each risk alloc­ated to one spe­cif­ic mem­ber of the team to take lead responsibility.
  • Aim through mit­ig­a­tion to reduce Like­li­hood (LL) mul­ti­plied by Impact (IM) risk score to below 10 as accept­able risk value.

Ref­er­ence key: A” items are risks impact­ing on all aspects of the Cor­por­ate Plan; C” items are Con­ser­va­tion only risks; V” risks relate spe­cific­ally to Vis­it­or Exper­i­ence; L” risk relate to Land Man­age­ment; R” risks relate to Rur­al Devel­op­ment risks.

Key:

  • Man­aged risk: (green down­ward arrow in greyed-out field): risk assess­ment that risk is effect­ively man­aged and no longer a stra­tegic risk pos­ing poten­tial to inhib­it achieve­ment of cor­por­ate stra­tegic object­ives. Risk can be removed from risk register.
  • Lower­ing risk: (green down­ward arrow): risk impact and / or like­li­hood is declin­ing res­ult­ing in over­all stra­tegic risk assess­ment of mit­ig­a­tion actions effect­ive with ongo­ing mon­it­or­ing of risk envir­on­ment still required.
  • Stat­ic risk: (amber hori­zont­al arrow): risk impact and like­li­hood is stable. Over­all stra­tegic risk assess­ment is stable indic­at­ing that stra­tegic risk remains, requir­ing ongo­ing man­age­ment and con­tin­ued imple­ment­a­tion of pro­posed mit­ig­a­tion and controls.
  • Increas­ing risk: (red upward arrow): risk impact and / or like­li­hood is increas­ing res­ult­ing in increas­ing risk of achieve­ment of stra­tegic object­ives being inhib­ited. Man­age­ment action, and pos­sibly resource invest­ment, required to address risk envir­on­ment and pos­sibly intro­duce new mit­ig­a­tion action, in order to reduce risk impact and / or likelihood.

Ver­sion Control:

  • 3 Board Cycle Decem­ber 2019
  • 3.0 Board adop­ted ver­sion June 2019 for MT / OMG review
  • 3.1 Audit Com­mit­tee review 6 Septem­ber 2019
  • 3.2 Man­age­ment Team Novem­ber 2019
  • 4 Board Cycle Jan to Jun 2020
  • 4.0 Draft fol­low­ing Board con­sid­er­a­tion Decem­ber 2019
  • 4.1 To Audit and Risk Com­mit­tee March 2020
  • 5 Board Cycle July to Sep 2020
  • 5.1 Sep 20 Board meet­ing draft for MT / OMG review
  • 5.2 Sep 20 Board meet­ing fol­low­ing MT / OMG edits (WBW)
  • 6 Board Cycle Octo­ber 20 to Decem­ber 20
  • 6.1 ARC Novem­ber 20 first draft
  • 7 Board Cycle Janu­ary to June 2021
  • 7.0 ARC April 2021 and SMT May 2021
  • 7.1 Board June 2021
  • 8 Board Cycle to Decem­ber 2021
  • 8.0 To SMT 24 Aug 21
  • 8.1 SMT 24 Aug 21 Updates
  • 8.2 SMT 18 Jan 22 review and updated
×