Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 1 of 9

For dis­cus­sion Title: Budget mon­it­or­ing Pre­pared by: Louise Allen, Head of fin­ance and Cor­por­ate Oper­a­tions Pur­pose This paper sets out an over­view of the Park Authority’s budget man­age­ment pos­i­tion at the end of the month 8 of the 202324 fin­an­cial year — 30 Novem­ber 2023.

Recom­mend­a­tions The Resources Com­mit­tee is asked to: a) Con­sider the budget man­age­ment pos­i­tion for 202324.

Over­view

  1. Appendix 1 provides a sum­mary of expendit­ure against the pro­filed budget. Over­all, cash expendit­ure is well with­in budget at 47% of the annu­al budget, and 83% of the phased budget for this 8‑month period.

  2. Expendit­ure on oper­a­tion­al plan activ­it­ies, either com­mit­ted or spent, was 60% of the annu­al budget. While this is a reas­on­able pos­i­tion 2/​3rds of the way through the fin­an­cial year, there remains £2.5m to be com­mit­ted in the final quarter of the year, and £4.7m of expendit­ure to be con­ver­ted to cash. In terms of ref­er­ence to com­mit­ment, this refers to deliv­ery plans where form­al paper­work is in place with­in the fin­ance sys­tem. Teams will have com­mit­ments in place with part­ners which they have yet to con­vert to a full” com­mit­ment with­in our fin­an­cial system:

To be com­mit­tedTo be con­ver­ted to cash
Peat­land restoration£1.337m£2.332m
Oth­er oper­a­tion­al aims£1.132m£2.337m
Total oper­a­tion­al plan£2.469m£4.669m

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 2 of 9

Budget changes

  1. A log of budget changes is shown in Appendix 3.

Staff and Board

  1. Staff costs for the 8 months were £3.45m. The phased budget of £3.44m has been weighted to account for staff whose payroll costs will become recov­er­able from Nation­al Lot­tery Her­it­age Fund through the Cairngorms 2030 pro­ject (C2030). Col­leagues whose payroll costs are cur­rently accoun­ted for as core expendit­ure, will be work­ing on the pro­ject in quarter 4, and their payroll costs are included in the pro­ject cost plan. Recov­ery of these costs through the pro­ject will reduce the cost of core payroll in the final quarter of the year.

  2. There remains pres­sure on the budget for staff costs. The organ­isa­tion is cur­rently under­tak­ing recruit­ment for C2030, and the final out­turn for staff costs will be affected by the tim­ing of appoint­ments, and wheth­er posts are filled intern­ally or extern­ally. There is some poten­tial for recruit­ment delays to ease this year’s pressures.

Pro­gramme management

  1. All pro­gramme man­age­ment costs have been recovered from extern­al funds as expec­ted. We have received con­firm­a­tion from Nation­al Lot­tery Her­it­age Fund that the Her­it­age Hori­zons Devel­op­ment Phase has been fully com­pleted and author­ised with­in their system.

Over­heads

  1. The budget for over­heads has been phased evenly across the year. Cur­rently, costs are run­ning ahead of the budget.

  2. Con­trib­ut­ors to this vari­ance include repairs and main­ten­ance (par­tic­u­larly to the fire detec­tion and alarm sys­tem), leg­al costs, power, and mileage. These costs will be kept under review dur­ing the final quarter and expendit­ure plans man­aged accordingly.

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 3 of 9

Oper­a­tion­al plan

  1. Over­all, expendit­ure on oper­a­tion­al plan activ­it­ies to the end of Novem­ber is a little over 26% the total budget for the year.

  2. The com­mit­tee is aware of the delays exper­i­enced by the Peat­land Team in let­ting con­tracts and com­men­cing pro­jects. Work has moved on since the last report in Septem­ber, and just under £2m was either com­mit­ted or spent at the end of Novem­ber. Form­al notice has been giv­en to Scot­tish Gov­ern­ment that we will be unable to use £500k of our £3.79m alloc­a­tion. In addi­tion, there are pro­jects that will be star­ted before the nest­ing sea­son but will need to be hal­ted and con­sequently, will not be com­pleted until after the fin­an­cial year end. These com­mit­ted amounts will be accrued into the 202324 fig­ures, allow­ing work on these pro­jects to con­tin­ue into early 202425.

  3. Expendit­ure on Nature and Cli­mate’ activ­it­ies con­tin­ues to increase, with the anti­cip­a­tion that the full budget will be used by the end of the year. Actu­al and com­mit­ted expendit­ure was 69% of the annu­al budget at the end of November.

  4. The budget towards our People’ aims is com­mit­ted to the extent of 84% of the annu­al budget. Annu­al grants for skills and train­ing (Cairngorms Busi­ness Part­ner­ship, Grow­biz, Coun­tryside Learn­ing Scot­land) have been com­mit­ted; resources for the youth action team and juni­or ranger activ­it­ies have been spent.

  5. Oper­a­tion­al plan activ­it­ies towards our Place’ aims include the devel­op­ment and improve­ment of path­ways. Grants have been com­mit­ted for all but £20k of this £350k budget for paths, but expendit­ure remains low, while we await claims against these awards. Nev­er­the­less, actu­al and com­mit­ted expendit­ure was close to 64% at the end of November.

  6. Com­mit­ment of the Cor­por­ate budget has been slow. We await plan­ning per­mis­sion for a new e‑bike shed. Plans for a dry­ing room for staff are in place. Expect­a­tions are that these pro­jects will be com­pleted before the year end.

  7. Most of the under­spend on Com­mu­nic­a­tions (£98k) relates to the devel­op­ment of the new web­site. The length of the pro­cure­ment pro­cess has pushed expendit­ure to the end of the year.

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 4 of 9

  1. At this point in the year, the expect­a­tion remains that, except for peat­land res­tor­a­tion pro­jects, the budget for oper­a­tion­al plan activ­it­ies will be spent in full.

Sum­mary of the pos­i­tion after 8 months

  1. The key points arising from the review of the fin­an­cial pos­i­tion at the end of Novem­ber 2023 are: a) Pres­sure on the budget for staff costs remains but may be ameli­or­ated by nat­ur­al recruit­ment delays. b) Over­head costs are run­ning ahead of the phased budget but will be man­aged with­in the con­text of the over­all annu­al budget. c) There are no con­cerns over the recov­ery of pro­ject costs. d) £500k of the budget alloc­a­tion towards peat­land res­tor­a­tion will not be drawn down. e) Expendit­ure on oper­a­tion­al plan activ­it­ies is expec­ted to be in line with budget. f) A peak of expendit­ure will occur in the final quarter of the year, in line with the trend in pre­vi­ous years.

Louise Allen louiseallen@​cairngorms.​co.​uk 17 Janu­ary 2024

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 5 of 9

Appendix 1 Sum­mary of expendit­ure against the pro­filed budget YEAR END­ING 31 MARCH 2024 ACTU­ALBUDGET 30 NOVEM­BER 2023 CAIRNGORMS NATION­AL PARK AUTHOR­ITY Resources Com­mit­tee: Paper 1, Annex 1. 26th Janu­ary 2024

Annu­al BudgetBudget adjust­mentsOut­turn fore­castPhased budget to 30 Novem­ber 23Actu­al at 30 Novem­ber 23(Under)/over phased budget% of Out­turn forecast
Staff costs4,841,000198,6505,039,6503,440,7673,448,9808,21368%
Board fees192,000-192,000128,000111,871(16,129)58%
5,033,000198,6505,231,6503,568,7673,560,851(7,916)68%
Pro­ject costs
Pro­ject costs1,141,000-1,141,000---0%
Pro­ject costs recovered(1,141,000)-(1,141,000)---0%
-------
Over­heads
Oth­er staff and board costs164,000-164,000133,833188,59454,761115%
Facil­it­ies costs520,000(143,230)376,770251,180247,187(3,993)66%
IT and pro­fes­sion­al costs261,000-261,000174,000173,082(918)66%
945,000(143,230)801,770559,013608,86349,85076%
Oper­a­tion­al plan (net)
Peat­land restoration4,328,000(1,036,000)3,292,0001,478,000959,970(518,030)29%
Nature & climate818,00050,000868,000419,420177,038(242,382)20%
People277,000-277,000178,750115,308(63,442)42%
Place865,00051,000916,000529,333273,373(255,960)30%
Cor­por­ate441,50062,000503,50096,12051,216(44,904)10%
Com­mu­nic­a­tions354,500(9,650)344,850192,20093,885(98,315)27%
Con­tri­bu­tion to Cairngorms 2030285,000(146,500)138,500---0%
7,369,000(1,029,150)6,339,8502,893,8231,670,790(1,223,033)26%
Total expendit­ure13,347,000(973,730)12,373,2707,021,6035,840,504(1,181,099)47%
Oth­er income(182,000)-(182,000)(115,333)(130,048)(14,715)71%
Cash expendit­ure13,165,000(973,730)12,191,2706,906,2705,710,456(1,195,814)47%
Grant-in-aid drawn down(13,151,000)957,000(12,194,000)(7,275,000)(7,275,000)-60%
Net cash expenditure/​(income)14,000(16,730)(2,730)(368,730)(1,564,544)(1,195,814)

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 6 of 9

Appendix 2 Oper­a­tion­al plan – com­mit­ted expendit­ure YEAR END­ING 31 MARCH 2024 OPER­A­TION­AL PLAN — COM­MIT­TED EXPENDIT­URE CAIRNGORMS NATION­AL PARK AUTHOR­ITY Resources Com­mit­tee: Paper 1, Annex 2. 26th Janu­ary 2024 67%

Annu­al budgetBudget adjust­mentsAmended budgetActu­al at 30 Novem­ber 23Com­mit­ted expendit­ureTotal — actu­al and com­mit­ted expendit­ureActu­al and com­mit­ted as per­cent­age of amended budget
Oper­a­tion­al plan
Peat­land restoration4,328,000(1,036,000)3,292,000959,970994,5321.954.50259%
Nature & climate818,00050,000868,000177,038414,435591,47368%
People277,000-277,000115,308117,574232,88284%
Place865,00051,000916,000273,373311,267584,64064%
Cor­por­ate441,50062,000503,50051,216118,770169,98634%
Com­mu­nic­a­tions354,500(9,650)344,85093,885105,169199,05458%
Con­tri­bu­tion to Cairngorms 2030285,000(146,500)138,500-138,500138,500100%
7,369,000(1,029,150)6,339,8501,670,7902,200,2473,871,03761%

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 7 of 9

Appendix 3 Log of Budget changes

  1. Since the budget was form­ally approved, there have been changes to the avail­ab­il­ity of fund­ing: a) we were able to pay for­ward on our 202324 com­mit­ment to Cairngorms 2030 (C2030), b) we have been made aware that our expect­a­tions for both cap­it­al and resource fund­ing to sup­port peat­land res­tor­a­tion may not be met, and c) the anti­cip­ated pay award for 202324, may exceed our budget pro­vi­sion. These changes are set out in appendix 2.
  2. In March 2023, we paid £150k from the 202223 budget to sup­port our com­mit­ment to C2030 for 202324 by provid­ing cash flow cov­er for the Devel­op­ment Phase activ­it­ies. This provided extra head­room in the 202324 budget. We have applied this to cov­er some areas of the budget that we felt, from fur­ther exam­in­a­tion of the detail of the likely costs, were under-resourced, such as the cost of our shared-ser­vices agree­ment with Loch Lomond and the Trossachs Nation­al Park Authority.
  3. £3.5k has been alloc­ated to cov­er a short exten­sion to the con­tract of the Green Health Link Work­er cur­rently engaged on the nature pre­scrip­tions pro­ject with­in the C2030 pro­gramme. This will allow con­tinu­ity of staff­ing, on what is a well- regarded pro­ject, for a short time after the end of the C2030 devel­op­ment phase (17 August 2023).
  4. Resource fund­ing for peat­land res­tor­a­tion is £614k, and this includes an alloc­a­tion to cov­er ele­ments of sup­port costs such as trans­port, office costs, and fin­ance and IT sup­port. In the first quarter of the year, this fund­ing was reduced to £510k, leav­ing the peat­land team with £104k less budget for non-staff costs than had been anti­cip­ated. Sub­sequently, this resource fund­ing was rein­stated by Scot­tish Government.
  5. At the same time, the cap­it­al budget for peat­land res­tor­a­tion was reduced by £507k to £3,636k. The pro­file of deliv­ery across the year has been such that a fur­ther £500k of the cap­it­al fund­ing for peat­land res­tor­a­tion will not be drawn down.

Cairngorms Nation­al Park Author­ity Ugh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 8 of 9

  1. Mod­el­ling of the impact of the poten­tial pay award indic­ates that our ori­gin­al budget estim­ate, made before the dir­ec­tion on the 202324 award had been determ­ined, is likely to require a fur­ther £85k of resources.
  2. Fur­ther space has been found with­in the 202324 budget. This arises from a change in the account­ing treat­ment we are required to apply to leases for prop­erty and vehicles. In the past these costs have been accoun­ted for as resource expendit­ure. We are now required to treat leased assets as cap­it­al items known as Right of Use’ (RoU) assets. The ini­tial recog­ni­tion of these RoU assets happened in the 202223 accounts, using cap­it­al budget (CDEL) spe­cific­ally provided to accom­mod­ate the new account­ing treat­ment. The change releases a little over £140k from the resource grant budget. New lease arrange­ments under­taken dur­ing the year will res­ult in cap­it­al expendit­ure. At present there is uncer­tainty around wheth­er these costs will be met by addi­tion­al budget from Scot­tish Gov­ern­ment. To ful­fil our cur­rent plans without addi­tion­al budget we will need to alloc­ate £160k from our dir­ect cap­it­al budget (£1,100k) to cov­er new vehicle leases and the renew­al of the Bal­later office lease. We will mon­it­or pro­gress on this budget pos­i­tion over the com­ing months.
  3. Payroll costs arising from exten­sion of the con­tracts of interns work­ing on com­mu­nic­a­tions pro­jects was paid for from the Com­mu­nic­a­tions resource budget, with a cor­res­pond­ing trans­fer to the staff costs budget.
  4. Addi­tion­al fund­ing (£50k) was received through the Nature Chal­lenge Fund.
  5. The adjus­ted pos­i­tion is a small sur­plus of £3k.

Cairngorms Nation­al Park Author­ity Ügh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh Resource Com­mit­tee Paper 1 26 Janu­ary 2024 Page 9 of 9

YEAR END­ING 31 MARCH 2024 Budget adjustments

Annu­al budgetAdvance to Cairngorms 2030Fund­ing reduc­tion Payroll — cov­erFund­ing reduc­tion peat­land cap­it­alFund­ing reduc­tion peat­land resourceLease account­ing poten­tial short­fallBudget adjust­ments Peat­land par­tial rein­state­ment of resource budgetGreen Health Link Work­er con­tract exten­sionExtend internsAddi­tion­al fund­ing Nature recov­eryPeat­land cap­it­al under­spendPeat­land resource fund­ing rein­statedRevised budget
Staff costs4,841,000-----85,000-9,650--104,0005,039,650
Board fees192,000-----------192,000
5,033,000-----85,000-9,650--104,0005,231,650
Run­ning costs
Oth­er staff and board costs164,000-----------164,000
Facil­it­ies costs520,000--(143,230)--------376,770
IT and pro­fes­sion­al costs261,000-----------261,000
945,000--(143,230)--------801,770
Oper­a­tion­al plan (net)
Peat­land restoration4,328,000(150,000)-(507,000)(104,000)-----(500,000)104,0003,292,000
Nature & climate818,000------3,500-50,000--868,000
People277,000-----------277,000
Place865,000-----------916,000
Cor­por­ate441,500-------(9,650)---503,500
Com­mu­nic­a­tions354,500-(37,000)---------344,850
Con­tri­bu­tion to Cairngorms 2030285,000----(143,230)------138,500
7,369,000(37,000)-(507,000)(104,000)--3,500-50,000(500,000)104,0006,339,850
Total expendit­ure13,347,000(37,000)---(143,230)85,0003,500-50,000(500,000)104,00012,373,270
Oth­er income(182,000)-----------(182,000)
Cash expendit­ure13,165,000(37,000)---(143,230)85,0003,500-50,000(500,000)104,00012,191,270
Grant-in-aid drawn down(13,151,000)-----------(12,194,000)
Net cash expenditure/​(income)14,000-----------(2,730)
×