240920Paper1Annex1Cairngorm2030projectmilestones2024
Cairngorms National Park Authority Ùghdarras Pàirc Nàiseanta a’ Mhonaidh Ruaidh
Performance Committee 20 September 2024
Page 1 of 1
Paper 1
Annex 1
Cairngorms 2030: Programme milestones
In column A: Blue Milestone wording has been changed Green Milestone added since last report Orange Milestone removed
In columns B‑E: Complete Milestone complete 31/08/2024 Milestone new since last report, or date has been added 31/08/2024 Milestone unchanged since last report 31/08/2024 Milestone has moved later but still within an appropriate timescale 31/08/2024 Milestone has moved later with concerns about the timeframe for delivery Milestone not noted in this quarter
Cairngorms 2030: Transforming landscapes Project / milestones | Planned completion as at —-| — -| — -| — -| — -| — -| | | end Q1 | end Q2 | end Q3 | end Q4
- Woodland expansion Glen Fender; fencing; Phase 1 planting; Phase 2 ground prep & planting | | | 31/12/2024 | Dalnamein; Phase 1 fencing & ground prep; Phase 2 fencing & ground prep | | | 31/12/2024 | Aspen; engage Trees for Life to do Cairngorms Aspen Network development; complete a framework and spatial plan for Cairngorms Aspen network | | | | 30/06/2025 Montane; complete nature networks opportunity mapping; assess suitability of Glenshee scheme; develop preferred scheme | | | | 31/12/2024 Riparian; complete nature networks opportunity mapping; develop preferred scheme | | | | 31/12/2024
- Peatland restoration Development phase — in progress (16 projects, Jan 24-Jun 24) | 13 | | | Development phase — complete (16 projects, Jan 24 ‑Jun 24) | 12 | | | Delivery phase — in progress (16 projects, March 24 — March 25) | 3 | 0 | | Delivery phase — complete (16 projects, March 24 — March 25) | 3 | 0 | | Closedown & completion in progress (16 projects, June 24 — March 25) | 2 | 0 | | Closedown & completion complete (16 projects, June 24 — March 25) | 2 | 0 | |
- Nature recovery Community Agri Damage (WGDMG): 1.1 Develop Grant t’s and c’s, agree and sign | May 2024 | Aug-24 | | 1.2 Confirm larder specs, place order for 2 larders | June 2024 | Aug-24 | | 1.3 Larder ground works, delivery, installation | Sept 2024 | Oct-24 | | 1.4 Begin cull, process venison, deliver to foodbanks/charities | Dec 2024 | Dec-24 | | C2030 Monitor Estate: 2.1 Develop and agree Expression of Interest (Eol), circulate to CNP landowners | May 2024 | Dec-24 | | 2.2 Identify projects/activities/budgets with landowner(s) and agree implementation schedule | June 2024 | Sep-24 | | 2.3 Develop matched funding and operational model with partner landowner(s) | Sept 2024 | Sept-24 | | South Deeside North Angus DMG: 3.1 Confirm riparian/catchment projects with SDNA members | May 2024 | Sep-24 | | 3.2 Confirm Glenmuick riparian project, manage bidding procedure, agree start date | Sept 2024 | Sep-24 | | West Grampian DMG: 4.1 Confirm delivery phase organisational structure with WGDMG Steering Group | May 2024 | Aug-24 | | 4.2 Confirm climate mitigation and biodiversity projects with WGDMG members, identify supporting activities and allocate budget | June 2024 | Complete | | South Grampian DMG: 5.1 Reserve £40K budget for potential FLS projects | Apr 2024 | Complete | | 5.2 Reallocate SGDMG budget to other NbS projects | Apr 2024 | Complete | |
- Cairngorms future farming Grant award letters signed | 09/04/2024 | Complete | | | Farm advice call-off contract on PCS | 16/04/2024 | Complete | | | Farm advisors appointed | 23/05/2024 | Complete | | | Farmers locked in at least 1 option to try | 28/11/2024 | | | 28/11/2024 Farmers carried out at least 1 option | 30/07/2025 | | | 30/07/2025
- Climate resilient catchments Upper Dee Pre-planning engagement complete | May 2024 | Complete | | | PoAN submitted | May 2024 | July 2024 | | | Major planning app submitted | August 2024 | Oct 2024 | | | Planning permission received | Nov 2024 | | | Jan 2025 Slugain Bridge procurement approach agreed with Highland Council — | April 2024 | Complete | | | Design consultant appointed | June 2024 | July 2024 | | | Planning app stage 1 submitted | Sept 2024 | Aug 2024 | | | Dalghety Buy-out or alternative process agreed to take forward | Nov 2024 | | | Nov 2024
- Green Finance and community wealth building Project Initiation Report | Complete | | | 29/3/2024 Develop Partnership agreements | | | 31/08/2024 | MoU agreed and signed | Complete | | | 20/6/2024 recruitment of GFO | 06/12/2024 | | | 06/12/2024 GFO appointment made | 3/5/2024 | | | 06/12/2024 Develop project scope | 31/7/2024 | | | 06/12/2024
- Landscape & communities Establish methodology | | | | 31/12/2027 Establish and maintain links with communities for engagement: Develop and establish Cairngorms landscape forum, champions and/or volunteers | | | 31/12/2024 | 31/12/2025 Stage one community engagement: online survey: Online survey development (including testing) | | | 30/09/2024 | 28/02/2025 Provisional identification, illustration and mapping of SLQs | | | | 31/12/2024
Cairngorms 2030: Empowerment Project / milestones | Planned completion as at —-| — -| — -| — -| — -| — -| | | end Q1 | end Q2 | end Q3 | end Q4
- Effective Community engagement Establish engagement team Train engagement team and C2030 staff | | | 30/06/2024 | Complete Develop working practices and engagement processes | | | 31/12/2024 | Develop plan of engagement for the first year | | 31/08/2024 | 31/08/2024 | Test and learn engagement models Citizens assembly (or equivalent form of participatory democracy) in proces | | 30/09/2024 | 30/09/2024 Gamification project established | | 31/12/2024 | 31/12/2024 Research innovative methods | | 31/12/2024 | 31/12/2024 Engagement working group meetings established | | 31/12/2024 | 31/12/2024 Develop engagement materials, working closely with comms colleagues | tbc | | | 31/12/2024 Establish and deliver engagement activity for year 1 | | | 31/12/2024 Evaluate, develop, refine — year 1 reflections | | | 31/12/2024 | 31/12/2024 Volunteering — managed by Volunteering Managers | | | 31/12/2024 | Map and build on relationships | | 31/12/2024 | 31/12/2024
- Climate learning & education School Engagement picked up with each partner school | | | | Shared Learning Event for School Staff before academic year end | 31/03/2024 | Complete | | James Ade inducted and work plan in place | | 30/06/2024 | Complete | | Engagement Platform Operational and being used by schools | | 30/06/2024 | Complete | | Yr1 Activity Plans in Place | | 30/06/2024 | Complete | | Yr. 1 Activity Plans underway | | 30/06/2024 | Complete | | Stories of Change Yr. 1 identified | | | 30/09/2024 | LfS School Activity Audit completed and being updated regularly | | | 30/10/2024 | 30/10/2024 | | | 15/12/2024 | 15/12/2024
- Climate conscious communities Contact Local Climate Hubs (x4) individually to share objectives and priorities and explore where we can support them and add value to their work and encourage activity in the National Park | | | 11/11/2024 | 11/11/2024 Contact Community Climate Groups to share objectives, knowledge re local networks / Hubs and explore where we can support them and add value to their activities | | 31/05/2024 | Complete | | Bring together Climate Hubs to share information and identify where we can add value to Hub areas in the Park, including pan Park | | 31/05/2024 | 01/11/2024 | Supporting activities and events taking place across the Park during Climate Week | | Complete | | Consider developing a web portal on new CNPA website to signpost communities to Climate Hubs, newsletters and funding opportunities dependent on timing of new website launch and capacity in digital comms team | | 30/09/2024 | 30/09/2024 | Finalise and deliver activity plan in collaboration with Climate hubs and other organisations across the National Park | | 30/09/2024 | 30/12/2024 |
- Community Arts & Culture Collaboration Workshops completed | | 28/08/2024 | | Yr. 1 Creative Activity Plan in place / approved | | 15/09/2024 | 15/09/2024 | | Yr. 1 Creative Activity Plan Launched | | 16/10/2024 | 16/10/2024 | | Yr. 1 Residency completed, and report approved | | 30/11/2024 | 30/11/2024 | |
- Community managed climate grants Employ Climate Grants Officer | | | 20/03/2025 | 20/03/2025 Induction of Climate Grants Officer & Admin Officer | | 31/03/2024 | Complete | | Test & learn across Climate Adaptation Fund — work with Community Grants team to test systems & processes. Fund set up by August 2024 | | 31/05/2024 | Complete | | Engagement and workup | | 31/08/2024 | | | Decision making process | | | 31/08/2024 | | Outputs and sharing | | 30/04/2024 | Complete | | Continue work with Social Value Engine & make recommendations | | 30/06/2024 | 31/12/2024 | | Research current climate funds available to communities within CNP & identify gaps | | 31/03/2025 | 31/03/2025 | Decision making | | | 30/09/2024 | Look at scope of £50k fund for 2024⁄25, work with engagement team & make recommendations to C2030 programme | | 30/09/2024 | 30/09/2024 | | Engagement and workup | | | 31/07/2024 | 31/07/2024 Outputs and sharing | | | 30/09/2024 | Write work plan — will inform the rest of the milestones — to include: | | | 31/12/2024 | 31/12/2024 M&E framework | | | 31/12/2025 | 31/12/2025 Engage with Lived Experience Group; lessons learned for EDI grants allocation. Process agreed by December 2024. | | 31/05/2024 | (Complete) | | | | | Complete | | | | | 31/12/2024 | 31/12/2024
Cairngorms 2030: Sustainable transport Project / milestones | Planned completion as at —-| — -| — -| — -| — -| — -| | | end Q1 | end Q2 | end Q3 | end Q4
- Cycle friendly Cairngorms Identify preferred supplier for E bike chargers | | | | Install 5 E‑Bike charging stations | | 31/07/2024 | 31/07/2024 | Promotional campaign to raise awareness of the new E bike chargers | | | 31/12/2024 | 31/12/2024 Deliver Skills sessions to minimum 2 primary schools | | | 31/12/2024 | 31/12/2024 Meet with relevant communities to develop support for community led loan schemes | | 30/06/2024 | 30/06/2024 | Trial scheme to allow rangers to use cargo bikes in 2 locations | | | | 31/03/2025 Attend minimum 3 public events to raise awareness of project | | 31/10/2024 | 31/10/2024 | | Procure preferred supplier/s for delivery of community training/skills sessions | | 30/09/2024 | 30/09/2024 | | Determine location for two Community led loan hubs | | | |
- Active Communities Recruit Sustainable Transport Manager | | | | 31/12/2024 Recruit Sustainable Transport Officer | | | | Recruit Graduate Transport Officer | | | | 31/12/2024 Prepare and Submit funding applications for Aviemore + 5 other communities. | | | | Secure construction funding grant offer for Dulnain Bridge NMU | 31/12/2024 | 31/12/2024 | Prepare ITT for design stages for PfE successful projects | | 31/12/2024 | 31/12/2024 | Procure and appoint consultants (where funding is secured) | 31/12/2024 | 31/12/2024 | Develop monitoring baseline for individual projects | | | Complete | Remainder to be defined once outcome of funding bids is known (expected April 24) | | | Complete |
- Sustainable travel P1 Persona development Detailed delivery plan complete | | | Complete | Personas V1.0 complete | | | | P2 DRT — Badenoch & Strathspey | | Sep-24 | Project delivery plan — sign-off | | Complete | Complete | DRT active in area | 14/06/2024 | | P3 Community Transport — Upper Deeside | 26/07/2024 | 17/01/2025 Project delivery plan — sign-off | | 13/10/2024 | | P4 Data and digital infrastructure | | 01/11/2024 | 31/12/2025 | National datasets — baselining complete | 05/07/2024 | 13/10/2024 | | Bus patronage data — baselining complete | | | 30/06/2025 | | P5 Glenmore Sustainable Transport Plan | | | 30/06/2025 | | Project re-initialisation complete | | | | Project delivery plan sign-off | | | | P6 Public Transport improvements | | 13/10/2024 | On hold | Bikes on buses — Partnership and funding package agreed (Aberdeenshire Council) | | | | Bus stops — existing infrastructure mapped | 12/07/2024 | | Aviemore Adventurer — opportunities for improvement documented | 16/08/2024 | | Engagement complete | | | |
- Changing travel behaviour Recruit Sustainable Transport Manager | | 01/10/2024 | 01/10/2024 | Recruit Sustainable Travel Behaviours Officer | | | | Opportunities for collaboration found and positive relationships built with partner organisations | | 01/10/2024 | 01/10/2024 | Detailed project planning complete | | 01/10/2024 | 01/10/2024 | Delivery of confidence building activities underway | | | | 5 events attended | | | | Initiatives to overcome barriers identified | | | | Promotion delivery underway | | | | Signage and wayfinding audit complete | 29/11/2024 | | Signage and wayfinding improvements underway | | | | Complete | | Complete | | 30/09/2024 31/12/2024 31/12/2024 31/12/2024 31/12/2024 31/12/2024
Cairngorms 2030: Health and wellbeing Project / milestones | Planned completion as at —-| — -| — -| — -| — -| — -| | | end Q1 | end Q2 | end Q3 | end Q4
- Wellbeing Economy Wellbeing economy action plan approval (WEAP), CNPA Board | | | | Track Indicators through C2030 projects — establish actual baselines with key projects during Q2. | | 30/09/2024 | 30/09/2024 | Develop resources — develop 2 case studies for WE In year 1 | | 30/06/2024 | Complete | | Engagement activity | | | 31/12/2024 | 31/03/2025 Annual monitoring check on WE Indicators, and ME work on WE within C2030, and wider WEAP | | | 31/12/2024 | |
- Public health & the outdoors Promote Green Health Week and use feedback to identify groups and opportunities that support the project | | | 31/12/2024 | 31/12/2024 Develop resources for Nature Prescription programme (including a welcome pack and indoor activity kit). | | | 31/12/2024 | 31/12/2024 Complete development of an appropriate programme of training for activity providers and local organisations, and commence delivery (future dates tbc) | 30/11/2024 | Complete | | | Establish average patient contact capacity patterns from referrals to inform ongoing planning and delivery | | 30/09/2024 | 30/10/2024 | | Roll out provider agreement for currently engaged relevant organisations across Badenoch and Strathspey | | 30/09/2024 | 31/12/2024 | | Risk Management procedures are developed and signed-off. | | 31/12/2024 | 31/12/2024 | |
- Outdoor dementia resource centre Output 1. The monthly program of activities will continue to develop | | | 31/12/2024 | 31/12/2024 Output 2A: Explore the possibility of creating a network of dementia friendly paths at Badaguish. | | | | Output 2B: Explore the possibility of obtaining more adaptive bikes for our participants to use. | | 29/05/2026 | 29/05/2026 Output 2C: The ODRC building will be a more dementia friendly environment | | 31/03/2025 | 31/03/2025 | Output 2D: A Green Health Referral pathway for people with dementia will be established locally | | | | | | | 31/03/2025 | 31/03/2025 Complete | | | | 31/12/2024 | 31/12/2024
Cairngorms 2030: Knowledge exchange Project / milestones | Planned completion as at —-| — -| — -| — -| — -| — -| | | end Q1 | end Q2 | end Q3 | end Q4
- Knowledge exchange and research Project tasks Appoint evaluation consultants | | | | Appoint and induct Knowledge Exchange Co-ordinator | 15/04/2024 | Complete | | | Appoint and induct PhD student | 13/05/2024 | Complete | | | M&E framework in place | 30/09/2024 | 30/09/2024 | | | M&E initial review with consultants | 11/06/2024 | 02/10/2024 | | | Monitoring plans for all projects | 01/08/2024 | 27/09/2024 | | | KE website | 02/08/2024 | 30/08/2024 | | | Data review for year 1 | 28/03/2025 | 29/07/2025 | | | Programme tasks Recruitment | 24/01/2025 | 24/01/2025 | | | Programme sharing — team day | 14/06/2024 | Complete | | | Quarterly reporting system | 23/04/2024 | Complete | | | Budget reporting system | 15/03/2024 | Complete | | | Risk reporting system | 29/03/2024 | Complete | | | Programme team review for year 1 | 29/03/2024 | 28/06/2024 | | | | 20/12/2024 | 20/12/2024 | | |