2022⁄23 Transitional Plans: January 2022 Submissions Consolidated
Summary of financial and staffing proposals
CAIRNGORMS NATIONAL PARK AUTHORITY
Formal Board Paper 2 25th March 2022
ANNEX 1: Financial Proposals
Financial Investment Proposals (£000) | Deployed FTE | Total FTE |
Nature & Climate | | |
Nature & Climate | 795 | 24.5 |
People | | |
People | 425 | 17.4 |
Place | | |
Place | 630 | 11.0 |
Corporate | | |
Corporate | 568 | 21.0 |
Communications | | |
Communications | 186 | 7.4 |
Total | 2,604 | 81.3 | 81.3 |
Transitional Plan Provision | | | |
Transitional Plan Provision | 2,092 | | |
Heritage Horizons Contribution | 150 | | |
Visitor Services Capital Prog | 324 | | |
COVID Corporate Response | 30 | | |
Total | 2,596 | 81.79 | 81.79 |
Surplus (Over Programmed) | (8) | 0.5 | 0.5 |
Cairngorms National Park Authority: Transitional Corporate Plan 2022⁄23
NATURE AND CLIMATE
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required (£000) | Staff Deployed FTE |
Delivering Net Zero by 2045 | Undertake carbon audit and establish 2022 baseline | Annual progress report on delivering Net Zero | A1: reach net-zero asap | | |
Woodland expansion and enhancement | Woodland challenge fund | 1,000ha new woodland; improving quality of existing native woodlands | | 55 | 1.20 |
Sustainable upland management | | 1,000Ha | A2: Increase woodland cover NPPP: A3 Restore & manage peatland; A4 reduce deer numbers; A5 reduce intensity of gamebird management; A6 muirburn Heritage Horizons: peatland, SLMP, Green Investment | 105 | 6.30 |
| Peatland restoration | | | | 1.90 |
| Deer management | Sustainable Land Management Plans | | | |
| East Cairngorms Moorland Partnership | Better understanding and demonstration of sustainable upland management | | | |
| Sustainable gamebird management | | | | |
Nature Networks | Supporting nature recovery projects | delivering on ‘call for sites’ from land managers and community-led projects | NPPP: A7 farm C & bio plans; A9 river restoration; A10 ecological network; A11% land managed for restoration; A13 designated sites contribute to network and restoration HH: Future farming, climate resilient catchments | 150 | 4.50 |
| Nature friendly farming | | | 180 | |
| Freshwater restoration | | | | |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required | Staff Deployed |
| Surveying & Mapping | strategic mapping of habitat and species corridors and connectivity | | | |
| Upland scrub/moorland fringe | | | | |
| Riparian corridors | | | | |
Species conservation: CNAP priority species | Cairngorms Capercaillie Project | progress along the Species Recovery Curve | A14: protect & enhance rare and vulnerable species | 155 | 4.30 |
| Cairngorms wildcat project | | | | 1.90 |
| Raptor project | | | | |
| Delivering the CNAP species plans | | | | |
Cairngorms Nature communictions and engagement | CN BIG weekend | Raised profile, awareness and understanding of conservation work in the Park; more involvement and support for conservation activities | CNAP: Involving people | 35 | 1.00 |
Landscape | Engagement pathways | | | | |
| Communications | | | | |
| Landscape toolkit, SLQ monitoring, attitudes and perceptions surveys/workshops | better understanding of special landscape qualities and perceptions of change | NPPP | 20 | 1.2 |
| Casework | advice to applicants and planning team | | | |
Cairngorms Nature Index & Biological data management | CNI, Atlas, support citizen science and biological recorders | good information and data available to guide long term conservation | A12: CNI | 75 | 1.2 |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required | Staff Deployed |
Landowner liaison and coordination | Regional Land Use Partnership/Framework, wildfire groups, Farmers Forum | Wildlifire plan(s) | A8: Regional Land Use Partnership & Framework | 20 | 1 |
Corporate functions & organisational development | | | | | |
| | | | 795 | 24.50 |
Cairngorms National Park Authority: Transitional Corporate Plan 2022⁄23
PEOPLE
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required | Staff Deployed |
Develop a Wellbeing Economy | Develop a well-being economy Cornerstone Indicators and Action Plan; Support for business | A plan and a suite of well-being economy indicators; No. of supported recovering businesses making transition. Mentoring scheme | NPPP B1 B2 B3 and C11; HH People Projects | 50 | 0.5 |
Skills, training and wages | Audit and plan to promote Living Wage; Skills initiative in place re. green jobs and hospitality | Audit of wages; Plan in place for skill development | NPPP B4 and B5; HH People Projects | 20 | 0.3 |
Promote community-led development and management of land /assets | Renew Community Action Planning process with Local Place Planning; Replace previous EU-sourced LEADER and structural funds; Support for community development projects; Community managed grant scheme | Refreshed set of Community Action Plans. Plus HH project targets | NPPP B6, B7, B8, B9; HH People Projects | 90 | 0.3 |
Community learning, participation and engagement | Climate Conscious Communities; Citizen assembly/Juries; Climate learning and education; Outreach and engagement; Community Grant scheme | HH Project Targets | NPPP B6 and B7; HH | 0 | 0.5 |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required | Staff Deployed |
Active Cairngorms | Develop Active Cairngorms Action Plan; Run Health Walks Programme; Public Health and outdoors; Dementia Activity Resource Centre | HH Project Targets; Mental health metrics; Activity levels of least active have increased | NPPP B11; HH People Projects | 0 | 0.30 |
Ranger Services | Manage CNPA Ranger Service & support & grant aid the family of Cairngorms Rangers | CNPA Rangers engage with 12,000 visitors; 13 partner services in place and providing consistent monitoring & messaging | NPPP/Corp | 165 | 12.40 |
Volunteering & Inclusion | Manage Volunteer Cairngorms and Vol. and Junior Rangers, support Health Walks and John Muir Awards; Cairngorms Youth Action Team & promote inclusion | 8 new volunteer rangers trained with 1000 volunteer days delivered; 1,000 JMA’s supported & 25 Junior Rangers trained | NPPP B13; | 95 | 2.10 |
Responsible Outdoor Access | Manage & support CLOAF, promote responsible outdoor access | Three CLOAF meetings; outdoor access duties | NPPP/Corp | 5 | 1.00 |
TOTALS | | | | 425.00 | 17.40 |
Cairngorms National Park Authority: Transitional Corporate Plan 2022⁄23
PLACE
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required | Staff Deployed |
Sustainable Tourism Action Plan | Develop new TAP to promote off-peak growth and spread visitors; investing in visitor management projects; investing in cultural/interpretation projects | Europarc validation visit and Charter awarded | NPPP C1 and C2 and C7 | 25 | 0.7 |
Sustainable Tourism Action Plan | Digital Information for visitor management | On line access to digital visitor information; digitial ranger information provision | | 75 | |
Places for Everyone Programme | With Sustrans, support partners developing active travel. HH Active travel projects. | Complete Strategic Network Study. Complete stages 1 and 2 for 9 community neighbourhoods plus Active Aviemore | NPPP C3 and C4; HH Place Projects | 0 | 0 |
Strategic Visitor Infrastructure Improvement Programme | Develop Strategic Infrastructure Plan; Support partners to improve visitor infrastructure; Develop systems to monitor and maintain key infrastructure | Plan submitted to VisitScotland; 6 key projects delivered; Grant to OATS | NPPP C5 and C6 | 350 | 0.5 |
Path maintenance and improvement | Maintain and improve Speyside Way, mountain paths and support core path maintenance | Infrastructure Plan agreed; Speyside Way Extension formally opened | NPPP C4 | 140 | 0.50 |
Cairngorm & Glenmore Priority Area | Deliver C and G Strategy; HH Glenmore Transport Plan | Lochside parking complete, public toilets replaced, IoT installed & working | NPPP; HH Place Projects | 20 | 0.3 |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH / Corporate) | Budget Required | Staff Deployed |
Improve availability of housing for workers in the NP | Investigate future land options for delivery of affordable and targeted housing; Support community-led housing group and projects; Use new tools for control of second homes | Reduction in second homes, vacant or short-term let properties; Percentage of developable land in community or public body ownership is increasing. | NPPP C8, C9, C10 | 10 | 2.5 |
Deliver an efficient Planning Service | Delivery & Monitoring of LDP; Development Management, Enforcement, reviewed advice and training for customers | Improvement priorities delivered; Monitoring Report | NPPP B1 and B2; Corp | 0 | 6 |
Delivering Net Zero by 2045 | Undertake carbon audit and establish 2022 baseline; Deliver and monitor NPPP | Annual progress report on delivering Net Zero; Park Partnership Plan approved | NPPP | 10 | 0.50 |
Totals | | | | 630.00 | 11.00 |
Cairngorms National Park Authority: Transitional Corporate Plan 2022⁄23
CORPORATE
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH/Corporate) | Budget Required | Staff Deployed |
National collaboration heightening positive awareness of national park | National Park Partnerships (NPP) Joint Communications and Fundraising activities supported | Positive communications gains through UK wide collaboration / non-core funding raised | Corporate | 21 | 0.05 |
Community Grant Scheme / Community Led Local Development Redesign | Develop ideas around future of community grant schemes and integrate with community participation through Citizens Assemblies | HH Community Grant Project developed to Delivery Stage end point B8 | HH Project 3c / NPPP | 0 | 1.20 |
Open, inclusive, innovative, professional organisation | Supporting effective staff consultation including any action on Fair Work policy | Effective staff engagement in organisational change processes | Corporate | 0 | 0.30 |
Open, inclusive, innovative, professional organisation | Staff survey evaluation / Organisational COVID response actions / Workforce management and organisational development activity | Organisational Development Strategy to underpin forward Corporate Plan 2023⁄27 | Corporate | 30 | 2.50 |
Open, inclusive, innovative, professional organisation | Board direct elections | Successful direct community elections to board | Corporate | 40 | 0.20 |
Open, inclusive, innovative, professional organisation | Equalities Training for staff and Board and Supporting on-site event for EAP | Effective staff engagement and underpinning ODS4/culture change | Corporate | 15 | 0.30 |
Open, inclusive, innovative, professional organisation — exemplar with regards climate change | Providing infrastructure to support Active Travel for staff and partners | Delivering net Zero | Corporate and NPPP | 30 | 1.00 |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH/Corporate) | Budget Required | Staff Deployed |
Open, inclusive, innovative, professional organisation | Shared services delivered through LLTNPA covering IT, Procurement and GIS | Effective, efficient IT, procurement and GIS service provision | Corporate | 152 | 0.10 |
Open, inclusive, innovative, professional organisation | Delivering Heritage Horizons and wider Programme and Project management across the organisation | Effective project management systems are in place supporting delivery of project outcomes across the organisation | Corporate / HH all activities / NPPP all activities | 150 | 3.00 |
| Supporting community led development of voluntary giving scheme and charitable investment in infrastructure and nature | Increased voluntary donations for nature conservation and access infrastructure | | | 0.40 |
Robust and secure IT and data infrastructure | Delivering IT infrastructure to meet IT Strategy and Organisational Development Strategy Objectives | Robust, secure IT services supporting effective dispersed working and hybrid office working | Corporate | 50 | 3.30 |
Robust and secure IT and data infrastructure | Establising data management, information security and customer relationship information protocols to support new working methods and changes in IT infrastructure | Clear data management and security principles in place and deployed by all staff providing robust open access to records and data | Corporate | 20 | 1.20 |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH/Corporate) | Budget Required | Staff Deployed |
Open, inclusive, innovative, professional organisation | Delivering effective governance support and advice across the organisation | Effective support to and operation of boards and committees; clarity of understanding of governance roles and responsibilities | Corporate | 10 | 1.80 |
| Facilities maintenance and improvements, including enhancement to support increased active travel by staff in their commute to office | Facilities in place to suport active travel to offices | Corporate | 50 | 1.10 |
Open, inclusive, innovative, professional organisation | Delivering high quality finance and adminstration support services across the organisation; to shared services clients and to community led organisations | Effective support in delivery of all strategic targets; achieve financial results | Corporate | | 4.50 |
TOTALS | | | | 568.00 | 20.95 |
Cairngorms National Park Authority: Transitional Corporate Plan 2022⁄23
COMMS
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH/Corporate) | Budget Required | Staff Deployed |
Organisational management and team leadership | | Team deliver against corporate plan targets and team morale is positive | NPPP / HH / Corporate | | 0.4 |
Raise awareness of, and support for, the work of CNPA and its partners | Proactively promote CNP / CNPA via local, national and international media and respond to ad hoc enquiries | Range of positive news coverage across a variety of print, online and broadcast channels | NPPP / HH / Corporate | 7.5 | 0.8 |
| Fully scope and begin development of a new CNP / CNPA website(s), while maintaining existing platforms | Detailed tender doc produced for new website(s) tied directly to core user journeys | NPPP / HH / Corporate | 50 | 1.4 |
| Build a community of active supporters through engaging content on our social media channels | Deepened engagement of key audiences, with content clearly delineated between channels | NPPP / HH / Corporate | 9 | 1.2 |
| Produce a range of corporate publications, interpretation and signage to promote key projects / activities (incl. NPPP4 / HH) | Publications produced to a consistently high standard on time and on budget | NPPP / HH / Corporate | 60 | 0.8 |
| Review the existing CNP / CNPA brand framework and produce a range of easy-to-use, fully accessible resources | Revised brand guidelines document plus comprehensive suite of templates produced | Corporate | 5 | 0.3 |
Develop and deliver a comprehensive stakeholder engagement programme | Conduct a thorough analysis of key audiences and use insights from this to inform all comms activity | Series of pen portraits for each audience which underpins year-round comms grid activity | NPPP / HH / Corporate | | 0.4 |
| Work with partners to encourage responsible visitor behaviour, including visiting out of season and lengthening their stay | Reduction in incidents of poor visitor behaviour; long-term trend of visitation outside core summer months | NPPP | | 0.5 |
| Develop, rollout and evaluate a series of stakeholder engagement events / opportunities tailored to key audiences | Engaging programme of events / opportunities developed; key audiences more informed about our activities | NPPP / HH / Corporate | 20 | 0.4 |
Strategic Objective | Work Package / Key Actions | Outcome / Target | Strategic Link (NPPP / HH/Corporate) | Budget Required | Staff Deployed |
| Develop a stakeholder engagement programme for Heritage Horizons and promote it effectively with stakeholders | Engagement programme delivered; key audiences more informed about our activities | HH | 9.5 | 0.4 |
Ensure all CNP / CNPA comms outputs are fully accessible and reach as broad a range of audiences as possible | Ensure our websites meet the strictest criteria for web content accessibility | Aim to achieve WCAG 2.0 AAA status, with a minimum of AA by the end of the year | NPPP / HH / Corporate | 10 | 0.2 |
| Work with partners to deliver comms campaigns that support and engage with under-represented groups in the Park | Greater engagement and participation from under-represented groups | NPPP / HH / Corporate | 10 | 0.2 |
| Provide advice, training and guidance to staff on producing accessible and inclusive materials / content | Range of practical ‘how to’ guides and training sessions delivered; staff feel more informed / equipped | NPPP / HH / Corporate | | 0.2 |
| Deliver a new five-year Gaelic Language Plan that provides increased opportunities for individuals and communities to engage with the language | New Gaelic Language Plan drafted, consulted on and signed off by BNG; key activities delivered; more people engage with language | NPPP | 5 | 0.1 |
Keep staff / board fully informed and engaged through high quality internal comms | Work with HR and Corporate Services to communicate effectively with staff, board, volunteers etc, keeping them up to date with all the latest developments | Staff, board, volunteers etc feel more informed and able to talk about work across CNP / CNPA | Corporate | | 0.1 |
TOTALS | | | | 186 | 7.4 |