Audit and Risk Committee meeting - Paper 1: Cover risk register - 14 November 2025
Audit and Risk Committee Paper 1 14 November 2025 Page 1 of 2
For discussion Title: Strategic risk registers Prepared by: Louise Allen, Head of Finance and Corporate Operations
Purpose This paper supports a review by the Committee of the Park Authority’s strategic risk management position.
Recommendations The Audit and Risk Committee is asked to: a) Consider the coverage and adequacy of the Park Authority’s strategic risk management position and advise on any gaps or amendments required to the current strategic risk register. b) Consider the coverage and adequacy of the Cairngorms 2030 programme risk management position and advise on any gaps or amendments required to the current programme risk register.
Executive Summary
The Cairngorms National Park Authority’s most recent strategic risk register, and strategic risk management position is set out in Annex 1. The register was last reviewed by the Executive on 17 October 2025. Amendments made are shown in purple text.
No risk scores have been amended. Comments and mitigation actions have been updated for Risk IDs 6, 13, 14,15 and 16.
There remain 13 active risks on the Strategic Risk Register.
The Cairngorms 2030 programme risk register, and risk management position is set out in Annex 2.
Audit and Risk Committee Paper 1 14 November 2025 Page 2 of 2
The total programme risk profile was changed from Green to Amber in March, to reflect the significant identified risks relating to funding for Active Communities transport projects (Risk ID Nos 2 and 7). This risk is now significantly reduced by the award of funding by Transport Scotland, and the letting of the contract for design work on the Active Communities projects. Consequently, risk 2 has been re- categorised from amber to green, and risk 7 from red to amber. Currently, risk 7 is the only one of the seven programme risks not rated green.
The amber rating for risk 7 arises from a condition of this funding, that it must be used by 31 March 2026. Consequently, the short timescale for completion of the work puts pressure on delivery. Continuation of these projects past the initial design stage will require a further award of funding for 2026⁄27.
The Committee is invited to consider the current coverage of the risk registers as set out In the Annexes. The Committee’s views on the current status of the risk registers are welcomed.
Louise Allen Louiseallen@cairngorms.co.uk 3 November 2025