Audit and Risk Committee Paper 2 Annex 2 - Cairngorms 2030 strategic risk register
Cairngorms 2030: Risk management
Project: Cairngorms 2030: Programme risk Project Manager: David Clyne Job title: Head of Cairngorms 2030 Date of last risk review: 22-Feb-24 Period: Q3 2024
| Risk ID No. | Date | Risk Description | Impact Description | Impact Level | Probability Level | Priority Level | Trend | Mitigation Strategy | Q1 25 | Q2 25 | Status | Owner | Date of last assessent | Reassessment Date | Forward look to Q3 25 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 14/12/2023 | Total programme risk profile | Programme delay or failure. Potential loss of match funding or partner support | 5 | 2 | 10 | Improving | Risk profile increased from green to amber Improving following notification from Sustrans Scotland that design stage funding is not available in 2024⁄25 Active Communities project risk profile remains at amber following notification from Sustrans Scotland that design stage funding is unavailable in 2024/2025. Funds not expected until 2025/2026. | Amber | Amber | OPEN | David Clyne | 25/07/2025 | 01/10/2025 | Transport funding decision and mitigation plan essential |
| 2 | 14/12/2023 | Future funding profile | Insufficient match funding to meet agreed commitments. | 5 | 2 | 10 | Improving | Revised smaller scale delivery plan approved by NLHF, Programme Board and Performance Committee Discussions continue with SG & Transport Scotland on importance of releasing funds asap to allow design work to commence Sustrans notifcation that TS funds are approved — await formal award. Quarterly cash flow and match funding monitoring review with project leads and finance team. | Amber | Amber | OPEN | David Clyne | 25/07/2025 | 01/10/2025 | Transport funding decision and mitigation plan essential |
| 3 | 14/12/2023 | Finance: impact on Park Authority budget management | The potential financial implications for C2030 Park Authority spend agreed at £450k pa. | 4 | 1 | 4 | No change | Programme delivery will be a key element of 25⁄26 budget scenario plans as board and management consider deployment of financial allocations for the next financial year | Green | Green | OPEN | David Clyne | 25/07/2025 | 01/10/2025 | Park Authority prepared to increase its core match funding in 25⁄26 to progress transport project if Sustrans/TS funding is not paid as planned. |
| 4 | 14/12/2023 | Procurement standards | All contracts must meet PCS standards. Possible legal challenge if regulations not met. | 3 | 2 | 6 | Improving | Procurement standards and project initiation approvals are being revised to improve compliance and decision making. | Green | Green | OPEN | David Clyne | 25/07/2025 | 01/10/2025 | Transport ITTs if funding approved |
| 5 | 14/12/2023 | Staffing | Insufficient staff in post impacts project delivery, timescales and outcomes | 4 | 2 | 8 | Improving | staff resignations — 2 | Amber | Green | OPEN | David Clyne | 25/07/2025 | 01/10/2025 | Full staff compliment |
| 7 | 14/12/2023 | Delivery of Sustrans funded projects | Sustrans/active travel match funding for the programme is not secured at the values or within the timelines required to achieve project objectives. | 5 | 2 | 10 | Improving | Sustrans notifcation that TS funds are approved — await formal award. Revised smaller scale delivery plan approved by NLHF, Programme Board and Performance Committee Sustrans/active travel match funding for the programme is not secured at the values or within the timelines required to achieve project objectives. Active Communities project risk profile remains at amber and project deliverables have been amended | Amber | Red | OPEN | David Clyne | 25/07/2025 | 01/10/2025 | Transport funding decision and mitigation plan essential |
Likelihood Outcome
- Rare (Low)
- Unlikely (Low)
- Possible
- Likely (High)
- Almost Certain