Audit and Risk Committee Paper 2 Annex 2 - Cairngorms 2030 strategic risk register

Cairngorms 2030: Risk management

Pro­ject: Cairngorms 2030: Pro­gramme risk Pro­ject Man­ager: Dav­id Clyne Job title: Head of Cairngorms 2030 Date of last risk review: 22-Feb-24 Peri­od: Q3 2024

Risk ID No.DateRisk Descrip­tionImpact Descrip­tionImpact LevelProb­ab­il­ity LevelPri­or­ity LevelTrendMit­ig­a­tion StrategyQ1 25Q2 25StatusOwn­erDate of last asses­sentReas­sess­ment DateFor­ward look to Q3 25
114/12/2023Total pro­gramme risk profilePro­gramme delay or fail­ure. Poten­tial loss of match fund­ing or part­ner support5210Improv­ingRisk pro­file increased from green to amber Improv­ing fol­low­ing noti­fic­a­tion from Sus­trans Scot­land that design stage fund­ing is not avail­able in 202425 Act­ive Com­munit­ies pro­ject risk pro­file remains at amber fol­low­ing noti­fic­a­tion from Sus­trans Scot­land that design stage fund­ing is unavail­able in 2024/2025. Funds not expec­ted until 2025/2026.AmberAmberOPENDav­id Clyne25/07/202501/10/2025Trans­port fund­ing decision and mit­ig­a­tion plan essential
214/12/2023Future fund­ing profileInsuf­fi­cient match fund­ing to meet agreed commitments.5210Improv­ingRevised smal­ler scale deliv­ery plan approved by NLHF, Pro­gramme Board and Per­form­ance Com­mit­tee Dis­cus­sions con­tin­ue with SG & Trans­port Scot­land on import­ance of releas­ing funds asap to allow design work to com­mence Sus­trans noti­fc­a­tion that TS funds are approved — await form­al award. Quarterly cash flow and match fund­ing mon­it­or­ing review with pro­ject leads and fin­ance team.AmberAmberOPENDav­id Clyne25/07/202501/10/2025Trans­port fund­ing decision and mit­ig­a­tion plan essential
314/12/2023Fin­ance: impact on Park Author­ity budget managementThe poten­tial fin­an­cial implic­a­tions for C2030 Park Author­ity spend agreed at £450k pa.414No changePro­gramme deliv­ery will be a key ele­ment of 2526 budget scen­ario plans as board and man­age­ment con­sider deploy­ment of fin­an­cial alloc­a­tions for the next fin­an­cial yearGreenGreenOPENDav­id Clyne25/07/202501/10/2025Park Author­ity pre­pared to increase its core match fund­ing in 2526 to pro­gress trans­port pro­ject if Sustrans/​TS fund­ing is not paid as planned.
414/12/2023Pro­cure­ment standardsAll con­tracts must meet PCS stand­ards. Pos­sible leg­al chal­lenge if reg­u­la­tions not met.326Improv­ingPro­cure­ment stand­ards and pro­ject ini­ti­ation approvals are being revised to improve com­pli­ance and decision making.GreenGreenOPENDav­id Clyne25/07/202501/10/2025Trans­port ITTs if fund­ing approved
514/12/2023Staff­ingInsuf­fi­cient staff in post impacts pro­ject deliv­ery, times­cales and outcomes428Improv­ingstaff resig­na­tions — 2AmberGreenOPENDav­id Clyne25/07/202501/10/2025Full staff compliment
714/12/2023Deliv­ery of Sus­trans fun­ded projectsSustrans/​active travel match fund­ing for the pro­gramme is not secured at the val­ues or with­in the timelines required to achieve pro­ject objectives.5210Improv­ingSus­trans noti­fc­a­tion that TS funds are approved — await form­al award. Revised smal­ler scale deliv­ery plan approved by NLHF, Pro­gramme Board and Per­form­ance Com­mit­tee Sustrans/​active travel match fund­ing for the pro­gramme is not secured at the val­ues or with­in the timelines required to achieve pro­ject object­ives. Act­ive Com­munit­ies pro­ject risk pro­file remains at amber and pro­ject deliv­er­ables have been amendedAmberRedOPENDav­id Clyne25/07/202501/10/2025Trans­port fund­ing decision and mit­ig­a­tion plan essential

Like­li­hood Outcome

  1. Rare (Low)
  2. Unlikely (Low)
  3. Pos­sible
  4. Likely (High)
  5. Almost Cer­tain
×