CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Agenda Item 11 Appendix | 24/09/2021
AGENDA ITEM 11
APPENDIX I
ACTION PROGRAMME
Cairngorms National Park Local Development Plan 2021 Action Programme
Cairngorms NATIONAL PARK
CONTENTS
Cairngorms National Park Authority Local Development Plan 2021
SECTION 1: PURPOSE AND FORMAT Purpose.. 1 Format. 1 The role of partners…. 2 Links to other Plans and Strategies.. 3 Abbreviations used in the Action Programme.. 4
SECTION 2: NATIONAL PROJECTS A9 Dualling. 5 Highland Mainline Rail improvements. 6 Review of Badenoch and Strathspey Healthcare facilities. 7
SECTION 3: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS Strathspey Railway Extension to Grantown. 8 Development of ‘Active Aviemore’ Project.. 9 An Camas Mòr……. 10 Cairngorm Mountain and Glenmore. 11
SECTION 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK. 12
SECTION 5: MONITORING. 17
SECTION 6: DEVELOPMENT LAND SUPPLY Aviemore. 19 Ballater… 27 Grantown-on-Spey. 31 Kingussie.. 35 Newtonmore. 40 Blair Atholl. 43 Boat of Garten… 46 Braemar. 48 Carr-Bridge. 54 Cromdale. 59 Dunlain Bridge. 63 Kincraig… 66 Nethy Bridge. 70 Tomintoul.. 72 Calvine.. 75 Dalwhinnie.. 76 Dinnet.. 78 Glenmore. 81 Inverdruie & Coylumbridge. 83 Laggan… 85
ACTION PROGRAMME 2021
Cairngorms National Park Authority Local Development Plan 2021
SECTION 1: PURPOSE AND FORMAT Purpose
This Action Programme has been prepared to support the delivery of the Cairngorms National Park Local Development Plan 2021 (LDP).
The aim of the Action Programme is to set out actions which will help implement the vision, strategy and proposals of the LDP. It is the Cairngorm National Park Authority’s (CNPA) main delivery tool for the LDP and will be used to help monitor progress.
The Town and Country Planning (Development Planning) (Scotland) Regulations 2008 requires Action Programmes to set out:
- A list of actions required to deliver each of the Plan’s key policies and proposals;
- The organisation who is to carry out the action; and
- The broad timescale for carrying out each action.
However, Action Programmes are now being promoted as a key tool for facilitating and supporting development delivery. Scottish Planning Policy (2014) emphasises that ‘Action programmes should be actively used to drive delivery of planned developments: to align stakeholders, phasing, financing and infrastructure investment over the long term’ (para. 31).
This Action Programme sets out progress updates on:
- National Projects within the National Park that will play a role in the future delivery of development and policy objectives of the LDP;
- Infrastructure and Other Projects that will support the delivery of the aims of the LDP; and
- How the LDP Policies will be implemented and monitored; and
- Individual site allocations by settlement. Each site is set out in Section 6, and a Red/Amber/Green system is used to evaluate their effectiveness.
All statutory Consultees have been consulted on this Action Programme to ascertain any additional information relating to the infrastructure requirements and any constraints which may affect the delivery of sites.
The CNPA use the Action Programme to build a clearer evidence base for the each of the allocated sites in the LDP, identifying constraints, or costs of developing sites and ways of resolving them. This will also include developer obligations requirements for each settlement.
This information will be updated annually through each review of the Action Programme and will be available for developers and communities.
Format
The Action Programme has six main sections:
Section | Page |
---|---|
1.The Purpose and Format | 1 |
2. National Projects | 5 |
3. Infrastructure Delivery and Other Projects | 8 |
4. Delivery of LDP Policy Framework | 12 |
5. Monitoring | 17 |
6. Development Land Supply Information | 18 |
ACTION PROGRAMME 2021
Page I
Cairngorms National Park Authority Local Development Plan 2021
SECTION 1: PURPOSE AND FORMAT
The role of partners
The Action Programme is prepared by the CNPA, however, the CNPA is only one of many stakeholders — including public bodies, private developers, landowners and communities — who are responsible for delivering actions within it.
For example, most local authorities combine the roles of planning authority with housing authority, roads authority, education authority and delivery of services, each of which may help deliver the LDP for an area. In the Cairngorms National Park, the local authorities continue to do all those roles, with the CNPA sharing parts of the planning authority role. This means that our Action Programme relies heavily on the work of the local authorities and other public bodies as well as the owners of land, private developers and communities. There are too many to identify in detail, but some of the key roles are summarised below:
Summary of partner roles | Partner | Responsible for: | | : — — — — — — — — — — — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | | Cairngorms National Park Authority | Coordination of delivery, monitoring and review of LDP and Action Programme. Significant planning consents, monitoring and enforcement, delivery of efficient planning service for customers Support and small-scale funding for corporate priorities | | Local Authorities | Planning consents, monitoring and enforcement, delivery of efficient planning service for customers. Housing authority role including Housing Strategies, Strategic Housing Investment Plans, assess Housing Need and Demand. Building Control, Roads, Waste, Education, Care services, Leisure, Business support, Environmental Health roles. | | NatureScot | Advice and support on Natural Heritage in preparation of LDP and in planning applications for planning authorities and developers. Regulation of Species Licences. Full details at : https://www.nature.scot/doc/planning-great-places | | Scottish Water | Infrastructure for and connections to public water supplies and waste water systems. Full details at www.scottishwater.co.uk | | Scottish Environment Protection Agency | Advice and support on Environmental issues in preparation of LDP and in planning applications for planning authorities and developers. Environmental Regulations and Licensing. Info: www.sepa.org.uk/environment/land/planning/ | | Enterprise agencies (HIE, Scottish Enterprise) | Engage in LDP preparation and consultations. Advice and support on sustainable economic and social development issues. | | Other public bodies | Advice and support during preparation of LDP and in planning applications for planning authorities and developers. May invest in projects or programmes that support or are connected to the LDP. | | Developers, (including community groups or Public bodies when acting as a developer) | Undertake work to make effective planning applications, including seeking pre-application advice. Comply with planning consents and conditions. Secure other required consents. Keep planning authority informed of progress or problems with sites. Secure funding, manage development process through to completion and disposal or sale of properties. | | Communities and other groups | Engage in LDP preparation and consultations. Develop and review Community Action Plans. Establish community development companies to coordinate and develop projects. |
ACTION PROGRAMME 2021
Page 2
Cairngorms National Park Authority Local Development Plan 2021
SECTION 1: PURPOSE AND FORMAT
Links to other Plans and Strategies
The Local Development Plan and Action Programme help to deliver the plans and strategies of many organisations and for many issues across the National Park. In particular, the Cairngorms National Park Partnership Plan which is the overarching land use strategy for the National Park. It therefore sets the context for:
- The Local Development Plan
- Active Cairngorms
- Cairngorms Nature
- The Economic Strategy
Review of the Action Programme
The CNPA will review and republish the Action Programme annually and want it to be a ‘live’ document that changes and adapts over time.
The annual Action Programme reviews will reflect changes on the ground, demonstrate progress or constraints in delivery, incorporate new actions and provide up to date information on the status and progress of sites over time along with current developer obligations requirements. Each annual review will be report to CNPA Planning Committee for information and will be published on the CNPA website for communities and developers.
Other plans and strategies that are linked to the National Park Partnership Plan and Local Development Plan also include:
- The local authorities’ Housing Strategies, and Strategic Housing Investment Plans
- Transport Scotland Strategic Transport Projects Review and Regional Transport Strategies
- Area Waste Plans
- Local Authority capital investment plans
- Community Action Plans
- Plans of Community Planning Partnerships
- Scotland’s River Basin Management Plan and Catchment Management Plans
This Action Programme however only focuses on projects that contribute to the delivery of the Local Development Plan 2021.
ACTION PROGRAMME 2021
Page 3
Cairngorms National Park Authority Local Development Plan 2021
SECTION 1: PURPOSE AND FORMAT
Abbreviations used in the Action Programme
There are a number of organisations and terms that are used in the Action Programme frequently. Their names or terms have been abbreviated at some points in the document and are listed below.
Organisations: | Other abbreviations: |
---|---|
CBP Cairngorms Business Partnership | DIA Drainage Impact Assessment |
FLS Forestry and Land Scotland | FRA Flood Risk Assessment |
HES Historic Environment Scotland | HRA Habitats Regulations Assessment |
HIE Highlands and Islands Enterprise | LDP Local Development Plan |
HITRANS Highlands and Islands Transport Partnership | NFM Natural flood management |
HLF Heritage Lottery Fund | SEA Strategic Environmental Assessment |
LAS All constituent Local Authorities | WWTW Waste Water Treatment Works |
NS NatureScot | |
RSPB Royal Society for the Protection of Birds | |
SEPA Scottish Environment Protection Agency | |
SS SportScotland | |
SW Scottish Water | |
SYHA Scottish Youth Hostelling Association | |
THC The Highland Council |
ACTION PROGRAMME 2021
Page 4
Cairngorms National Park Authority Local Development Plan 2021
SECTION 2: NATIONAL PROJECTS
TABLE 2: NATIONAL PROJECTS identified through the Scottish Government’s National Planning Framework (NPF3) | Proposal | Description | Timescale | Lead Agency | Other Partners | Notes | | : — — — - | : — — — — — | : — — — — | : — — — — — | : — — — — — — - | : — — | | A9 Dualling | Transport Scotland is taking forward design and construction of the A9 Dualling between Perth and Inverness. The project is being developed with a view to completing the overall dualling to: * improve the operational performance of the A9 by reducing journey times and improving journey time reliability, improve safety for motorised and non-motorised users by reducing accident severity and reducing driver stress, facilitate active travel within the corridor, and improve integration with public transport facilities. | By 2025 | Transport Scotland | | CNPA and Highland Council removed objections to the Dalraddy to Slochd section of the A9 Dualling when Transport Scotland agreed to fund the planning and development of an alternative non-motorised user route between Aviemore and Carrbridge. A virtual public engagement was held November/December 2020 to present emerging route options. All information that was on display is published here: https://www.transport.gov.scot/projects/aviemore-to-carrbridge-non-motorised-user-route-study/ (transport.gov.scot) The preferred non motorised user route is expected to be announced late summer 2021. |
ACTION PROGRAMME 2021
Page 5
SECTION 2: NATIONAL PROJECTS
Cairngorms National Park Authority Local Development Plan 2021
TABLE 2: NATIONAL PROJECTS identified through the Scottish Government’s National Planning Framework (NPF3) | Proposal | Description | Timescale | Lead Agency | Other Partners | Notes | | : — — — - | : — — — — — | : — — — — | : — — — — — | : — — — — — — - | : — — | | Highland Mainline Rail improvements | Transport Scotland, on behalf of Scottish Ministers is working with Network Rail to develop phase two of the scheme which aims to deliver: * an hourly service; average journey time reductions of around 10 minutes between Inverness and Perth extended to Edinburgh and Glasgow; and more efficient freight operations that better respond to the needs of customers. | By 2025 | Transport Scotland | Network Rail | Phase 2 completed in May 2019. The long-term goal of the Highland Mainline enhancements programme seeks to achieve a fastest journey time of 2 hours 45 minutes between Inverness and the Central Belt with an average journey time of 3 hours and an hourly service by 2025. Further information available at: https://www.transport.gov.scot/projects/highland-main-line/project-details/ |
ACTION PROGRAMME 2021
Page 6
Cairngorms National Park Authority Local Development Plan 2021
SECTION 3: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS
The infrastructure projects which are needed to deliver the vision of the LDP and projects that will support it.
TABLE 3.1: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS IN LDP | Settlement/Project Name | Infrastructure/Project Description | Status/Constraints | Timescale | Lead Agency | Other Partners | | : — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — | : — — — — | : — — — — — | : — — — — — — - | | HIGHLAND | | | | | | | Review of Badenoch and Strathspey Healthcare facilities | As part of a NHS Highland review of healthcare facilities provision in Badenoch & Strathspey, there is a proposal to replace the existing hospital facilities in Grantown-on-Spey and Kingussie with new community hospital facility in Aviemore (image of proposed development below). The future uses of the old hospital facilities and land still to be identified. | Planning permission (2018/0311/DET) now approved for the site and funding secured. Site currently under construction. | 2020 onwards | NHS Highland | CNPA, THC, Medical Practices, Communities |
ACTION PROGRAMME 2021
Page 7
Cairngorms National Park Authority Local Development Plan 2021
SECTION 3: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS
The infrastructure projects which are needed to deliver the vision of the LDP and projects that will support it.
TABLE 3.1: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS IN LDP | Settlement/Project Name | Infrastructure/Project Description | Status/Constraints | Timescale | Lead Agency | Other Partners | | : — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — | : — — — — | : — — — — — | : — — — — — — - | | HIGHLAND | | | | | | | Strathspey Railway Extension to Grantown | Strathspey Railway Company’s project ‘Rails to Grantown’, is focussed on bringing steam railway to Grantown-on-Spey from Broomhill. Project also requires crossing of A95 Trunk road, with opportunities for upgrading a section of the A95 and off-road link between Dulnain Bridge and Grantown-on-Spey. | EIA scoping completed and TAWS application comprising the road crossing, railway and railway station to be submitted. | 2020 onwards | Strathspey Railway Co | Transport Scotland |
ACTION PROGRAMME 2021
Page 8
Cairngorms National Park Authority Local Development Plan 2021
SECTION 3: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS
The infrastructure projects which are needed to deliver the vision of the LDP and projects that will support it.
TABLE 3.1: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS IN LDP | Settlement/Project Name | Infrastructure/Project Description | Status/Constraints | Timescale | Lead Agency | Other Partners | | : — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — | : — — — — | : — — — — — | : — — — — — — - | | HIGHLAND | | | | | | | Development of ‘Active Aviemore’ Project | The Scottish Government has agreed to fund the construction of a new £15m hospital in Aviemore. CNPA has identified this investment as a catalyst to deliver other strategic developments including Active Aviemore. This project aims to improve Aviemore’s walking and cycling infrastructure, promote active travel and enhance the integration of social and health care facilities. Other infrastructure actions to support this include: Recruiting a CNPA infrastructure engineer. Preparing a five year CNP Infrastructure Plan. Commencing Heritage Horizons Active Travel and Sustainable Transport projects. | The project has now been divided into a number of independent projects to be delivered as follows: Grampian Road/Dalfaber Drive Junction — redesign and construction Community consultation underway (June 2021) Path upgrade from Primary School to new Hospital site (rail underpass) – design and construction. | 2021 – 22 | THC | Sustrans | | | | Designs submitted to Network Rail. Awaiting permissions and asset transfer process. Segregated cycle paths on Grampian Road. Design funding secured. Community consultation to re-commence |2021 – 22|Hitrans|CNPA, Aviemore & Vicinity Community Council| | | |Segregated cycle paths on Grampian Road Design funding secured. Community consultation to re-commence |2022 – 2025|CNPA|NLHF, Sustrans, THC, Hitrans, Aviemore & Vicinity Community Council|
ACTION PROGRAMME 2021
Page 9
Cairngorms National Park Authority Local Development Plan 2021
SECTION 3: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS
The infrastructure projects which are needed to deliver the vision of the LDP and projects that will support it.
TABLE 3.1: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS IN LDP | Settlement/Project Name | Infrastructure/Project Description | Status/Constraints | Timescale | Lead Agency | Other Partners | | : — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — | : — — — — | : — — — — — | : — — — — — — - | | HIGHLAND | | | | | | | An Camas Mòr | Development of a new community (1500 houses; associated business, community facilities and provision of infrastructure). Infrastructure required will include: * Road infrastructure, access and connectivity; Servicing infrastructure e.g. water, waste water, electricity; and Natural heritage, landscape and recreation. | Application under Section 42 to vary condition I of Planning Permission in Principle (CNPA Ref 09/155/CP) recommended for approval in August 2017. Section 75 signed and permission issued in April 2019. Awaiting submission of detailed Design and MSC applications for infrastructure. | 2021 onwards | An Camas Mòr LLP/The Highland Council/Aviemore Community Council | CNPA, NS |
ACTION PROGRAMME 2021
Page 10
Cairngorms National Park Authority Local Development Plan 2021
SECTION 3: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS
The infrastructure projects which are needed to deliver the vision of the LDP and projects that will support it.
TABLE 3.1: INFRASTRUCTURE DELIVERY AND OTHER PROJECTS IN LDP | Settlement/Project Name | Infrastructure/Project Description | Status/Constraints | Timescale | Lead Agency | Other Partners | | : — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — | : — — — — | : — — — — — | : — — — — — — - | | HIGHLAND | | | | | | | Cairngorm Mountain and Glenmore | The Cairngorm Masterplan which sets out the 25 year vision for the Mountain Estate was published in June 2021. The Masterplan comprises a 10 key strategies that will shape development of the publicly-owned Cairngorm Estate. It will act as a framework shaping future plans for ecology, sustainable transport, mountain biking, electrification, facilities development and more. The overarching vision for the Estate will be: ‘a world-class mountain environment where nature thrives and people of all ages and abilities enjoy access to outdoor sport, recreation and education opportunities in every season of the year’ (HIE). A key associated project is the SSEN power upgrade to Cairngorm which will increase electricity capacity in the area and enable the delivery of proposals within the masterplan to be delivered. | There are 10 key strategies which form the Cairgorm Masteplain including: An all-year round sustainable operating model Cohesive ecology and habitat restoration Promote active travel and sustainable transport (with specific focus on the Aviemore/Glenmore/Cairngorm corridor) A mountain for all providing diverse activities, uplift and facilities to cater for all user groups Scottish Centre for the Mountain Environment Excellent visitor experience Mountain biking De-carbonise the mountain Access from Ptarmigan Monitoring implementation of new activities | 2021 — 2046 onwards | HIE, SYHA, SSEN | CNPA, The Highland Council, SS, NS, Highlife Highland, Scottish Government |
ACTION PROGRAMME 2021
Page 11
Cairngorms National Park Authority Local Development Plan 2021
SECTION 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK The work that is needed to ensure the policy framework of the LDP is delivered.
TABLE 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK | Policy | Timescale | Description | How it will be delivered / monitored | Lead and Partners | | : — — — — — — — — — — — — — — — — — - | : — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | | All policies | 2021 onwards | Publish annual LDP monitoring and review report. | Report will be published annually. | CNPA | | Policy 1: New Housing Development | 2021 onwards | Ongoing review of LDP allocated sites, consents and land supply effectiveness and constraints. | Through the annual updates of the Action Programme and Housing Land Audits. | CNPA with input from developers, landowners, LA’s and communities | | | 2021 onwards | Undertake detailed community-based assessments of housing needs as appropriate where communities led housing projects. | Through the delivery of community led housing projects. | Housing Enabling Organisations and Community Support | | | | In addition, assist communities actively looking for ‘self-help’ solutions and work with these communities to help deliver specific projects. | Work ongoing with five communities currently taking forward projects at various stages of development to delivery community owned housing. | Organisations in conjunction with Community Groups, CNPA, LA’s, landowners and developers. | | | 2021 | Draft Housing Development Statutory Supplementary Guidance has been prepared and will be published for consultation in the Summer 2021. | Once adopted, the Supplementary guidance will be monitored through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LA’s | | | | Once consulted on, amendments may be made and it will be approved at Committee before getting final approval from the Scottish Government. | This will be an ongoing process. | |
ACTION PROGRAMME 2021
Page 12
Cairngorms National Park Authority Local Development Plan 2021
SECTION 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK The work that is needed to ensure the policy framework of the LDP is delivered.
TABLE 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK | Policy | Timescale | Description | How it will be delivered / monitored | Lead and Partners | | : — — — — — — — — — — — — — — — — — — - | : — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — | : — — — — — — — — | | Policy 2: Supporting Economic Growth | 2021 | Undertake an Economic Land Audit within the Park to review demand and supply for business land and unit availability within the National Park. | This project is currently underway. | CNPA | | | 2021 | Non-statutory planning guidance has been prepared, consulted on and adopted to support the | Ongoing monitoring through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LAs | | | | interpretation and delivery of business and economic related developments. | | | | | 2021 onwards | Re-start Town Centre Health checks to monitor the vitality and viability of town centres. | Preparation of a Town Centre Health Check Report published every two years. | CNPA, LAs | | | | Health checks were previously undertaken every two years, however have not been done since 2018 due to the pandemic. | | | | Policy 3: Design and Placemaking | 2021 | Promote good practice in terms of design through | Through the preparation of planning advice and using the CNPA website to highlight case studies. | CNPA in conjunction with LA’s, developers and communities. | | | | the preparation of Planning Advice, holding Design Awards and using case studies. | | | | | | Draft Design and Placemaking Statutory Supplementary Guidance has been prepared and will | Once adopted, the Supplementary guidance will be monitored through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LAs | | | | be published for consultation in the Autumn/Winter 2021. Once consulted on, amendments may be made | This will be an ongoing process. | | | | | and it will be approved at Committee before getting final approval from the Scottish Government. | | |
ACTION PROGRAMME 2021
Page 13
Cairngorms National Park Authority Local Development Plan 2021
SECTION 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK The work that is needed to ensure the policy framework of the LDP is delivered.
TABLE 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK | Policy | Timescale | Description | How it will be delivered / monitored | Lead and Partners | | : — — — — — — — — — — — — — — — — — — — — — | : — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | : — — — — — — — — | | Policy 4: Natural Heritage | 2021 | Non-statutory planning guidance has been prepared, consulted on and adopted to support the | Ongoing monitoring through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LA’s | | | | interpretation of the Policy and ensure development projects do not adversely affect Natural Heritage | | | | | | interests. | | | | Policy 5: Landscape | 2021 onwards | Continue to promote and apply the Landscape Toolkit for the Park. | Through individual assessment of planning applications. | CNPA | | | 2021 | Non-statutory planning guidance has been prepared, consulted on and adopted to support the | Ongoing monitoring through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LAs | | | | interpretation of Policy 5 and ensure developments fully consider and assess any landscape impacts. | | | | Policy 6: The Siting & Design of Digital Communications Equipment | 2021 onwards | Monitor consents and development on the ground — particularly in relation to 5G installations. | Ongoing monitoring through planning applications and feedback from CNPA, LAs and other consultees. | CNPA | | Policy 7: Renewable Energy | 2021 onwards | Monitor consents and development on the ground. | Ongoing monitoring through planning applications and feedback from CNPA, LAs and other consultees. | CNPA | | | 2021 | Non-statutory planning guidance has been prepared, consulted on and adopted to support the | Ongoing monitoring through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LAs | | | | interpretation of Policy 7 and guide the delivery of Renewable Energy related developments. | | |
ACTION PROGRAMME 2021
Page 14
Cairngorms National Park Authority Local Development Plan 2021
SECTION 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK The work that is needed to ensure the policy framework of the LDP is delivered.
TABLE 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK | Policy | Timescale | Description | How it will be delivered / monitored | Lead and Partners | | : — — — — — — — — — — — — — — — — — - | : — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — — — — — — — — — — — — — — — — - | | Policy 8: Open Space, Sport & Recreation | 2021 | Non-statutory planning guidance has been prepared, consulted on and adopted to support the | Ongoing monitoring through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LA’s | | | | interpretation of Policy 8 and guide developments affecting or relating to open space, sport or | | | | | | recreation. | | | | Policy 9: Cultural Heritage | 2021 | Review of conservation areas and management plans | Support or feed into the preparation of any Conservation Area Management | LA’s with input from CNPA and community. | | | onwards | as appropriate. | Plans. | | | | 2021 | Non-statutory planning guidance has been prepared, | Ongoing monitoring through planning applications and feedback from CNPA and LA Planning Officers. | CNPA, LAs | | | | consulted on and adopted to support the | | | | | | interpretation of the Policy and ensure development projects do not adversely affect any Cultural | | | | | | Heritage interests. | | | | Policy 10: Resources | 2021 | Monitoring consents and development on the | Ongoing monitoring through planning | CNPA with SEPA, NS, SW and Catchment Management | | | onwards | ground. | applications and feedback from CNPA, | Partnerships | | | | | LAs and other consultees. | | | | 2021 | Non-statutory planning guidance has been prepared, | Ongoing monitoring through planning | CNPA, LAs | | | | consulted on and adopted to support the | applications and feedback from CNPA | | | | | interpretation of Policy 10 and guide the delivery of | and LA Planning Officers. | | | | | resource related developments. | | |
ACTION PROGRAMME 2021
Page 15
Cairngorms National Park Authority Local Development Plan 2021
SECTION 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK The work that is needed to ensure the policy framework of the LDP is delivered.
TABLE 4: DELIVERY OF LOCAL DEVELOPMENT PLAN POLICY FRAMEWORK | Policy | Timescale | Description | How it will be delivered / monitored | Lead and Partners | | : — — — — — — — — — — — — — — — — | : — — — — — — | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — - | : — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — — | | Policy 11: Developer Obligations | 2021 onwards | Annually reviewing information to inform developer obligations requirements in terms of | Using the annual review of the Action Programme and preparation of | CNPA in conjunction with LA’s, Health Boards and relevant key agencies. | | | | education (school roll forecasts), healthcare and community facilities to give developers most up to | Supplementary Guidance. | | | | | date position on the contributions required. | | | | | 2021 | Draft Housing Development Statutory Supplementary Guidance has been prepared and will | Once adopted, the Supplementary guidance will be monitored through planning applications and feedback | CNPA, LAS | | | | be published for consultation in the Autumn/Winter 2021. Once consulted on, amendments may be made | from CNPA and LA Planning Officers. | | | | | and it will be approved at Committee before getting final approval from the Scottish Government. | This will be an ongoing process. | | | Community Information | 2021 onwards | Continuing to support communities to achieve their community objectives through Community Action | Through the delivery of Community Action Plans. | CNPA in conjunction with community support organisations | | | | Planning and Community Plan Partnerships. | | |
ACTION PROGRAMME 2021
Page 16
Cairngorms National Park Authority Local Development Plan 2021
SECTION 5: MONITORING
The routine monitoring of the LDP and Action Programme. This will be reported in the review of the Action Programme and other routine monitoring reports each year.
TABLE 5: MONITORING | Action / Description | Timescale | Lead Agency | Other Partners | | : — — — — — — — — — — — — — — — — | : — — — — | : — — — — — | : — — — — — — - | | Delivery of Action Programme | Annually | CNPA | LAS | | Use of Policies | Annually | CNPA | LAs | | Planning Permissions and Completions | Annually | CNPA | LAs | | Housing Land Supply and Effectiveness | Annually | CNPA | LAs | | Town Centre Health Checks | Every 2 years | CNPA | LAs | | SEA — Monitor environmental effects of LDP | Annually | CNPA | Key agencies | | HRA – Mitigation measures and effects on conservation objectives of European sites | Annually | CNPA | Key agencies |
ACTION PROGRAMME 2021
Page 17
Cairngorms National Park Authority Local Development Plan 2021
SECTION 6: DEVELOPMENT LAND SUPPLY
This section of the Action Programme is used to assess progress and identify constraints or barriers to the development of land and sites for housing, employment and community or other uses. It is set out by settlement and includes ‘anticipated infrastructure & affordable housing requirements’ which apply at a settlement level as well as more detailed updates on a site-by-site basis. These have been informed through consultation with the relevant authorities and each site has been colour coded to reflect its level of constraint.
The requirements set out in this Action Programme should be read in conjunction with the Local Development Plan 2021 particularly for information on mitigation requirements and assessments including the need for species protection plans, construction method statements and recreation management plans.
This section includes all current allocations