Paper 7 - Annex 1 Procurement Action Plan
Audit and Risk Committee Paper 7 Annex 1 20 June 2025 Page 1 of 4
Procurement Action Plan
Action to date
Report ref | Management action | Target date | Responsible officer | Progress | Date of review/comment |
---|---|---|---|---|---|
1.1 | Provide formal training for staff | 30.06.25 30.09.25 | Louise Allen/Mikko Saari | Discussion of formal training options for wider staff group is in progress (Scotland Excel). | 09.06.25 |
2.2 3.1 3.2 | Formalise controls: • Approvals required at each stage of procurement process • Formal evaluation process • Required due diligence checks | 31.12.24 30.09.25 | David Cameron | Project initiation guidance is in preparation (DFC). | 09.06.25 |
4.1 | Develop procurement KPIs | 31.03.25 31.12.25 | Louise Allen/Mikko Saari | To be developed as part of regular reporting schedule. | 09.06.25 |
Audit and Risk Committee Paper 7 Annex 1 20 June 2025 Page 2 of 4
Completed items
Report ref | Management action | Target date | Responsible officer | Progress | Date of review/comment |
---|---|---|---|---|---|
All | Further discussion of offering from Central Government Procurement Shared Services (CGPSS) team and Scotland Excel | Ongoing | Louise Allen | Relationship with Scotland Excel (SE) continues to develop well. Membership of SE in place providing access to their procurement frameworks COMPLETE | 25.10.24 |
1.1 | Draft strategy received from Loch Lomond and the Trossachs National Park Authority (LLTNPA) | 30.06.24 | David Cameron | The procurement strategy was approved by the Audit and Risk Committee 27/09/24. COMPLETE | 25.10.24 |
All | Procurement officer in post | 30.09.24 | Louise Allen | Mikko Saari in post 19/08/24 and working through probation. COMPLETE | 25.10.24 |
Audit and Risk Committee Paper 7 Annex 1 20 June 2025 Page 3 of 4
Report ref | Management action | Target date | Responsible officer | Progress | Date of review/comment |
---|---|---|---|---|---|
1.1 2.1 2.2 3.1 | Update policies and procedures. Include: • Process flow for different procurement thresholds • Explanation of each step in the procurement route • Approvals and levels of authority Delegated Levels of Authority (DLA) | 31.03.25 | Louise Allen/Mikko Saari | Procurement Guidance document approved by ARC. COMPLETE | 09.06.25 |
2.2 3.1 3.2 | Formalise controls: • Approvals required at each stage of procurement process • Formal evaluation process • Required due diligence checks | 31.12.24 | Louise Allen/Mikko Saari | Procurement Guidance document sets out what is required of staff, the financial limits determining the procurement journey and links to the organisation’s DLA policy. COMPLETE A central Procurement site has been set up in SharePoint, where all procurement documentation will be retained. COMPLETE Evaluation processes managed by the Procurement Officer. COMPLETE | 09.06.25 |
Audit and Risk Committee Paper 7 Annex 1 20 June 2025 Page 4 of 4
Report ref | Management action | Target date | Responsible officer | Progress | Date of review/comment |
---|---|---|---|---|---|
2.1 | Draft templates for each stage of the procurement journey | 31.03.25 | Louise Allen/Mikko Saari | Ongoing development of tailored resources for use by Park Authority colleagues continues as processes mature. COMPLETE (but will develop further over time) Links to templates are included in the Procurement Guidance document noted above. COMPLETE | 09.06.25 |
2.1 | Review existing contracts and prepare schedule for retendering | 31.03.25 30.09.25 | Louise Allen/Mikko Saari | COMPLETE | |
1.2 | Develop reporting for procurement activity | 30.09.25 | Louise Allen/Mikko Saari | Procurement Overview list has been prepared using Microsoft Lists. This will form a basis for the reporting of procurement activity. COMPLETE | 09.06.25 |
1.2 | Set up contracts register | 30.09.25 | Louise Allen/Mikko Saari | Contract Register list has been prepared using Microsoft Lists. COMPLETE | 09.06.25 |