Risk Assessment CNPA Planning Committee Site Visit to proposed Distillery site on Friday 13 September 2019
Task / Work activity /operation Description: CNPA Planning Committee Site Visit to proposed Distillery site on Friday 13 September 2019.
Bus drives members to Craggan Outdoors car park to visit site then return to Grantown on Spey CNPA officers following site visit. Any members of public attending to make their own way to car park to meet there.
Location: Aviemore
Date of assessment: Review date: 03/09/19 Assessors: Katherine Donnachie
Signature:
Number | Hazards: e.g. Trailing cable | Persons & numbers exposed | Harm: e.g. Tripping over cable and spraining ankle. | Risk Rating Without Controls | Controls E.g. re route cable or cover with cable tidy | Risk Rating With Controls |
---|---|---|---|---|---|---|
C L R | C L R | |||||
1 | Road and traffic, driving to site | Members of the CNPA Planning Committee and Staff. | RTA’s and collisions | 5 1 5 | 1. Party will be transported by minibus 2. Planning staff/Planning Committee Convener will brief all present on safe conduct required. | 5 1 5 |
2 | Weather – cold and/or wet | Members of the CNPA Planning Committee and Staff. | Exposure | 4 1 4 | 1. Advise members to wear appropriate clothing for the conditions. 2. Distance of total walk will be around 10 – 15 minutes so little chance of long exposure to weather. | 4 1 4 |
3 | Weather – high winds, storm | Members of the CNPA Planning Committee and Staff | Collisions with blown and falling objects, including tree | 4 1 4 | 1. Distance of total walk will be around 10 – 15 minutes so little chance of long exposure to weather. | 4 1 4 |
6 | Uneven or slippery including forest debris | Members of the CNPA Planning Committee and Staff | Slips, trips and falls | 4 2 8 | 1. Staff leading site visit will be familiar with the route and choose a route and pace suitable for the group. 2. Participants will be briefed to take care for uneven or slippery paths/surfaces. . 3. Staff attending site visit to carry a mobile phone to contact emergency services in case of accident. 4. Staff will advise participants to seek medical advice following any slips, trips or falls, supporting where required. | 4 2 8 |
Further Recommendations | Additional controls that would further reduce the risk if Implemented in the future. | Date to be Actioned by | Date Completed | | — -| — -| — -| | | | |
PPE Requirement
[PPE Images Omitted for brevity]
Risk Assessment
CNPA Planning Committee Site Visit to proposed Distillery site on Friday 13 September 2019
Risk Rating Key
Likelihood (L) | Consequence © | ®Overall Risk Rating |
---|---|---|
1 Very Unlikely | 1 Insignificant | 17 – 25 Unacceptable |
2 Unlikely | 2 Minor | 10 – 16 Tolerable |
3 Fairly Likely | 3 Moderate | 5 – 9 Adequate |
4 Likely | 4 Major | 1 – 4 Acceptable |
5 Very likely | 5 Catastrophic |
Checked by: Gavin Miles Signature: Position: Head of Planning & Communities .