210910AuCtteePaper1AAInternalAuditProgressReportSeptember21 FINAL
Cairngorms National Park Authority
Internal Audit Progress Report
September 2021
AV AZETS
CAIRNGORMS NATIONAL PARK AUTHORITY Audit & Risk Committee Paper | 10/09/21
Cairngorms National Park Authority
Internal Audit Progress Report
Summary 1 2021⁄22 audit plan progress 2
Summary
This paper provides the Audit and Risk Committee with a summary of internal audit activity since its last meeting and confirms the reviews planned for the coming quarter, identifying any changes to the annual plan. We have completed fieldwork on one audit since the last Audit and Risk Committee meeting: Leader administration and have commenced fieldwork on follow up part 1. We remain on track to deliver our Internal Audit plan as agreed.
Status of internal audit reviews 2021⁄22
(Pie chart showing: 5 Fieldwork Complete; 1 Fieldwork in progress; 1 Planning)
Plan for next quarter
The following reports are due to be presented to the October 21 Audit and Risk Committee:
- Leader Administration
- Follow Up Part 1
Action for Committee
The Audit and Risk Committee is asked to note the contents of this report and to approve the plan for the next quarter. We also invite any comments on the format or content of this report.
Chris Brown, Audit Partner Chris.Borwn@azets.co.uk 0131 473 3500 Stephanie Hume, Senior Manager Stephanie.Hume@azets.co.uk 01463 704 866
azets.co.uk
2021⁄22 audit plan progress
Ref and Name of report | Quarter | Current status | Planned ACC | Actual ACC |
---|---|---|---|---|
A1. Financial Management and Reporting | Q3 | Planning | Mar 22 | |
B1. Assurance Mapping of Major Projects | Q3 | Planning | Mar 22 | |
D1. ICT Strategy | TBC | Planning | TBC | |
D3. Cyber Security | TBC | Planning | TBC | |
E1. Leader Administration | Q2 | Fieldwork Complete | Oct 21 | |
E2. Follow up Part 1 | Q2 | Fieldwork | Oct 21 | |
E2. Follow up Part 2 | Q3 | Planning | Mar 22 | |
Annual report | N/A | N/A | May 22 |
Key:
Description |
---|
Complete: Audit work complete and report has been agreed and finalised |
Draft Report: A draft report has been issued |
Fieldwork complete: The audit work is complete but the draft report has not yet been issued. |
Fieldwork in progress: The audit work is in progress. |
Planned: The scope and timing of the audit has been agreed with management |
Planning: The scope and/or timing of the audit has yet to be agreed with management |
© Azets 2021. All rights reserved. Azets refers to Azets Audit Services Limited. Registered in England & Wales Registered No. 09652677. VAT Registration No. 219 0608 22.
Registered to carry on audit work in the UK and regulated for a range of investment business activities by the Institute of Chartered Accountants in England and Wales.