220527AuCtteePaper1AAICTStrategyReviewCover

220527AuCtteePaper1AAICTStrategyReviewCover
This document contains an internal audit report on the Cairngorms National Park Authority's ICT strategy. The audit, conducted by Azets, found four areas needing improvement. All recommendations for improvement have been accepted, with actions, responsibilities, and timetables outlined. Two recommendations had high-risk exposure and two were moderate. Two control objectives were achieved, but with room for improvement, while two more were not achieved due to inadequate controls. The Audit and Risk Committee is asked to review the report's findings and endorse the management's response.
Please be aware that this summary has been generated using AI.
×

We want your feedback

Thank you for visiting our new website. We'd appreciate any feedback using our quick feedback form. Your thoughts make a big difference.

Thank you!