Cairngorms National Park Authority Ughdarras Pàirc Nàiseanta a’ Mhonaidh Ruaidh
Resources Committee Paper 1 Appendixes 11 August 2023 Page 1 of 3
Appendix 1 Summary of expenditure against the profiled budget
YEAR ENDING 30 JUNE 2024 ACTUAL v BUDGET 30 JUNE 2023
CAIRNGORMS NATIONAL PARK AUTHORITY Resources Committee: Paper 1, Annex 1. 11th August 2023
Annual budget | Budget adjustments | Outturn forecast | Phased budget to 30 June 23 | Actual at 30 June 23 | (Under)/ over phased budget | % of Outturn forecast | |
---|---|---|---|---|---|---|---|
Staff costs | 4,841,000 | 85,000 | 4,926,000 | 1,184,135 | 1,176,970 | (7,165) | 24% |
Board fees | 192,000 | - | 192,000 | 48,000 | 39,816 | (8,184) | 21% |
- | 5,033,000 | 85,000 | 5,118,000 | 1,232,135 | 1,216,786 | (15,349) | - |
Project costs | - | - | - | - | - | - | - |
Project costs | 1,141,000 | - | 1,141,000 | - | - | - | 0% |
Project costs recovered | (1,141,000) | - | (1,141,000) | - | - | - | 0% |
- | 0 | 0 | 0 | 0 | 0 | 0 | - |
Running costs | - | - | - | - | - | - | - |
Other staff and board costs | 164,000 | - | 164,000 | 41,000 | 60,808 | 19,808 | 37% |
Facilities costs | 520,000 | (143,230) | 376,770 | 94,193 | 86,181 | (8,012) | 23% |
IT and professional costs | 261,000 | - | 261,000 | 65,250 | 51,974 | (13,276) | 20% |
- | 945,000 | (143,230) | 801,770 | 200,443 | 198,963 | (1,480) | - |
Operational plan (net) | - | - | - | - | - | - | - |
Peatland restoration | 4,328,000 | (536,000) | 3,792,000 | 15,000 | 17,606 | 2,606 | 0% |
Nature & climate | 818,000 | - | 818,000 | 54,000 | 35,153 | (18,847) | 4% |
People | 277,000 | - | 277,000 | 56,250 | 34,780 | (21,470) | 13% |
Place | 865,000 | 51,000 | 916,000 | 78,770 | 45,274 | (33,496) | 5% |
Corporate | 441,500 | 62,000 | 503,500 | 8,000 | 25,086 | 17,086 | 5% |
Communications | 354,500 | - | 354,500 | 40,400 | 22,853 | (17,547) | 6% |
Contribution to Cairngorms 2030 | 285,000 | (146,500) | 138,500 | 0 | 0 | 0 | 0% |
- | 7,369,000 | (569,500) | 6,799,500 | 252,420 | 180,752 | (71,668) | - |
Total expenditure | 13,347,000 | (627,730) | 12,719,270 | 1,684,997 | 1,596,501 | (88,496) | 13% |
Other income | (182,000) | - | (182,000) | (45,500) | (78,903) | (33,403) | 43% |
Cash expenditure | 13,165,000 | (627,730) | 12,537,270 | 1,639,497 | 1,517,598 | (121,899) | 12% |
Grant-in-aid drawn down | (13,151,000) | 611,000 | (12,540,000) | (1,880,000) | (1,880,000) | 0 | 15% |
Net cash expenditure/(income) | 14,000 | (16,730) | (2,730) | (240,503) | (362,402) | (121,899) | - |
Cairngorms National Park Authority Ughdarras Pàirc Nàiseanta a’ Mhonaidh Ruaidh
Resources Committee Paper 1 Appendixes 11 August 2023 Page 2 of 3
Appendix 2 Budget changes
YEAR ENDING 31 MARCH 2024 Budget adjustments
Annual budget | Budget adjustments | Revised budget | ||||||
---|---|---|---|---|---|---|---|---|
Advance to Cairngorms 2030 | Funding reduction — peatland resource | Payroll — cover Lease accounting potential shortfall | Peatland partial reinstatement of resource budget | Green Health Link Worker contract extension | ||||
Staff costs | 4,841,000 | - | - | 85,000 | - | - | 4,926,000 | |
Board fees | 192,000 | - | - | - | - | - | 192,000 | |
- | 5,033,000 | 0 | 0 | 85,000 | 0 | 0 | 5,118,000 | |
Running costs | ||||||||
Other staff and board costs | 164,000 | - | - | - | - | - | 164,000 | |
Facilities costs | 520,000 | - | (143,230) | - | - | - | 376,770 | |
IT and professional costs | 261,000 | - | - | - | - | - | 261,000 | |
- | 945,000 | 0 | (143,230) | 0 | 0 | 0 | 801,770 | |
Operational plan (net) | ||||||||
Peatland restoration | 4,328,000 | - | (104,000) | - | 75,000 | - | 4,299,000 | |
Nature & climate | 818,000 | - | - | - | - | - | 818,000 | |
People | 277,000 | - | - | - | - | - | 277,000 | |
Place | 865,000 | - | 51,000 | - | - | - | 916,000 | |
Corporate | 441,500 | - | 62,000 | - | - | - | 503,500 | |
Communications | 354,500 | - | - | - | - | - | 354,500 | |
Contribution to Cairngorms 2030 | 285,000 | (37,000) | (150,000) | - | - | 3,500 | 101,500 | |
- | 7,369,000 | (37,000) | (104,000) | 0 | 75,000 | 3,500 | 7,306,500 | |
Total expenditure | 13,347,000 | (37,000) | (104,000) | (143,230) | 85,000 | 75,000 | 3,500 | 13,226,270 |
Other income | (182,000) | - | - | - | - | - | (182,000) | |
Cash expenditure | 13,165,000 | (37,000) | (104,000) | (143,230) | 85,000 | 75,000 | 3,500 | 13,044,270 |
Grant-in-aid drawn down | (13,151,000) | - | 104,000 | - | - | - | (13,047,000) | |
Net cash expenditure/(income) | 14,000 | (37,000) | 0 | (143,230) | 85,000 | 75,000 | 3,500 | (2,730) |
Cairngorms National Park Authority Ughdarras Pàirc Nàiseanta a’ Mhonaidh Ruaidh
Resources Committee Paper 1 Appendixes 11 August 2023 Page 3 of 3
Appendix 3 Operational plan investment
Aim | Budget £’000 | Actuals Q1 £’000 | Forecast Q2 £’000 | Forecast Q3 £’000 | Forecast Q4 £’001 | Legally Committed Q1 £’000 |
---|---|---|---|---|---|---|
A3 Peatland restoration | 3,792,000 | 17,607 | 572,191 | 1,608,624 | 1,593,578 | 635,096 |
A2 Woodland expansion | 10,000 | 0 | 0 | 5,000 | 5,000 | 0 |
Д4 Deer and herbivore impacts | 40,000 | 2,000 | 4,000 | 14,000 | 20,000 | 0 |
A5 Moorland management | 40,000 | (292) | 4,000 | 18,000 | 18,292 | 0 |
A6 Gamebird management | 30,000 | 1,202 | 0 | 28,798 | 0 | 0 |
A8 Farming | 40,000 | 2,043 | 20,957 | 9,500 | 7,500 | 16,650 |
A9 Freshwater restoration | 150,500 | 9,268 | 8,732 | 117,000 | 15,500 | 30,000 |
A10 Ecological network | 91,900 | 6,363 | 23,065 | 36,472 | 26,000 | 10,000 |
A11 Ecological restoration | 113,000 | 0 | 50,000 | 30,000 | 33,000 | 0 |
A12 Cairngorms Nature Index | 68,500 | 153 | 26,000 | 27,500 | 14,847 | 0 |
A13 Species recovery | 198,000 | 11,045 | 67,251 | 64,704 | 55,000 | 30,500 |
A14 Green investment | 20,000 | 0 | 10,000 | 10,000 | 0 | 7,500 |
B1 Working-age population | 10,000 | 5,169 | 4,831 | 0 | 0 | 0 |
B4 Skills and training | 90,000 | 12,250 | 35,500 | 26,250 | 16,000 | 0 |
B7 Community-led planning and development | 107,000 | 5,000 | 74,000 | 17,000 | 11,000 | 0 |
B9 Mental and physical health | 10,000 | 0 | 4,000 | 0 | 6,000 | 0 |
B11 Volunteering and outdoor learning | 80,000 | 12,361 | 23,260 | 25,000 | 19,379 | 0 |
C1 Access to housing | 20,000 | 0 | 0 | 0 | 20,000 | 0 |
C2 New housing | 20,000 | 0 | 5,000 | 7,500 | 7,500 | 0 |
C5 Visitors to the National Park | 40,000 | 4,953 | 11,000 | 10,000 | 14,047 | 0 |
C8 Accessible path and cycle network | 583,250 | 19,405 | 115,230 | 250,995 | 197,620 | 128,950 |
C9 High quality visitor experience | 227,750 | 20,916 | 19,939 | 99,895 | 87,000 | 166,214 |
C10 Cultural heritage | 15,000 | 0 | 0 | 7,500 | 7,500 | 0 |
Comms | 262,900 | 26,224 | 53,852 | 55,992 | 126,832 | 45,860 |
Corporate | 799,700 | 25,086 | 177,756 | 228,190 | 368,669 | 369,257 |
- | 6,859,500 | 180,753 | 1,310,564 | 2,697,920 | 2,670,264 | 1,440,027 |
- | - | 3% | 19% | 39% | 39% | - |