240621ARCPaper7Annex2_C2030 programme risk register
Risk ID No. | Date | Risk Description | Impact Description | Impact Level | Probability Level | Priority Level | Trend | Mitigation Strategy | Risk Status | Risk Owner | Reassessment Date |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | 14/12/2023 | Total programme risk profile | Programme delay or failure | 5 | 2 | 10 | No change | Delivery phase contract signed by Park Authority and NLHF. Q1 2024 progress reports submitted to NLHF to schedule | OPEN | David Clyne | 01/08/2024 |
2 | 14/12/2023 | Future funding profile | Insufficient match funding to meet agreed commitments | 5 | 2 | 10 | No change | Monthly budget review with Finance Team. Theme Leads to agree mitigation plan and help identify alternative funding solutions. £3m Peatland restoration funding secured for 2024 | OPEN | David Clyne | 01/08/2024 |
3 | 14/12/2023 | Finance: impact on Park Authority budget management | Park Authority spend limited to £450k pa. | 4 | 1 | 4 | No change | Monthly budget review with Finance Team | OPEN | David Clyne | 01/08/2024 |
4 | 14/12/2023 | Procurement standards | All contracts must meet PCS standards. Possible legal challenge if regulations not met. | 3 | 2 | 6 | No change | Procurement guidance issued to staff and standards enforced. Recruit new CNPA Procurement Officer or external resource. | OPEN | David Clyne | 01/08/2024 |
5 | 14/12/2023 | Staffing | Insufficient staff in post impacts project delivery, timescales and outcomes | 4 | 2 | 8 | No change | Internal recruitment completed. External recruitment near completion with one post to fill. All posts in place by end May 2024. | OPEN | David Clyne | 01/08/2024 |
6 | 14/12/2023 | Project execution and NLHF second phase application timescales | Failure to submit high quality second phase NLHF application results in loss of funding. | 5 | 2 | 10 | No change | Application submitted on time | CLOSED | David Clyne | 29/03/2024 |
7 | 14/12/2023 | Delivery of Sustrans funded projects | CNPA has been notified of structural funding reform from Transport Scotland/Sustrans, which may present core funding opportunity. | 5 | 3 | 15 | No change | Ongoing challenge aligning NLHF and Sustrans delivery timescales. Discussions are ongoing at a senior level with Sustrans and Transport Scotland to ensure the Park Authority receives the same funding designation as local authorities. | OPEN | David Clyne | 01/08/2024 |