240927ARCtteePaper6Annex2RiskRegisters

Audit and Risk Com­mit­tee Paper 6 Annex 2

27 Septem­ber 2024

Risk IDDateRisk Descrip­tionImpact Descrip­tionImpact LevelProb­ab­il­ity LevelPri­or­ity LevelTrendMit­ig­a­tion StrategyRisk StatusRisk Own­erReas­sess­ment DateNote
114/12/2023Total pro­gramme risk profilePro­gramme delay or failure5315Det­or­i­at­ingRisk pro­file increased from green to amber fol­low­ing noti­fic­a­tion from Sus­trans Scot­land that design stage fund­ing is not avail­able in 202425OPENDav­id Clyne31/10/2024
214/12/2023Future fund­ing profileInsuf­fi­cient match fund­ing to meet agreed commitments5315Det­or­i­at­ingAs above. Meet­ing with Trans­port Scot­land to explore altern­at­ive fund­ing mod­els which has giv­en con­fid­ence that fund­ing will be secured albeit with a delay which may span Q3 to Septem­ber and pos­sibly into Q4. Theme lead con­tin­ues to dir­ect team on essen­tial pre­par­at­ory work and there­fore fund­ing delays are not crit­ic­al depend­an­cies at this stage.OPENDav­id Clyne01/08/2024
314/12/2023Fin­ance: impact on Park Author­ity budget managementPark Author­ity spend lim­ited to £450k pa.414No changeMonthly budget review with Fin­ance TeamOPENDav­id Clyne01/08/2024
414/12/2023Pro­cure­ment standardsAll con­tracts must meet PCS stand­ards. Pos­sible leg­al chal­lenge if reg­u­la­tions not met.326No changeNo issues. New Pro­cure­ment Officer has been recruited by Park Authority.OPENDav­id Clyne01/08/2024
514/12/2023Staff­ingInsuf­fi­cient staff in post impacts pro­ject deliv­ery, times­cales and outcomes428No changeEmpower­ment theme lead now on mater­nity leave and second­ment cov­er in place. Peat­land resor­a­tion man­ager has resigned from his post, with replace­ment now in postOPENDav­id Clyne01/08/2024
614/12/2023Pro­ject exe­cu­tion and NLHF second phase applic­a­tion timescalesFail­ure to sub­mit high qual­ity second phase NLHF applic­a­tion res­ults in loss of funding.5210No changeApplic­a­tion sub­mit­ted on timeCLOSEDDav­id Clyne29/03/2024
714/12/2023Deliv­ery of Sus­trans fun­ded projectsSustrans/​active travel match fund­ing for the pro­gramme is not secured at the val­ues or with­in the timelines required to achieve pro­ject objectives.5315No changeAct­ive Com­munit­ies pro­ject risk pro­file ini­tially increased from amber to red fol­low­ing noti­fic­a­tion from Sus­trans Scot­land that design stage fund­ing was not avail­able in 2024/2025 and pending final res­ol­u­tion of situ­ation noted above.OPENDav­id Clyne31/10/2024A meet­ing was organ­ised with Trans­port Scot­land to explore altern­at­ive fund­ing mod­els. Fol­low­ing reas­sur­ances received at this meet­ing, the risk around trans­port fund­ing has been reclas­si­fied to amber while con­tinu­ing to show risk escal­a­tion pending receipt of more form­al feedback

Job title: Head of Cairngorms 2030 Pro­ject Man­ager: Dav­id Clyne Date of last risk review: 22-Feb-24

×