Item7UpdateBroomhillQuarry20180140DET
CAIRNGORMS NATIONAL PARK AUTHORITY Planning Committee Agenda Item 7 28/06/2019
CAIRNGORMS NATIONAL PARK AUTHORITY
FOR DECISION
Title: POST COMMITTEE UPDATE – APPLICATION FOR
DETAILED PLANNING PERMISSION UNDER
SECTION 42 (2018/0140/DET) BROOMHILL QUARRY,
DULNAIN BRIDGE, GRANTOWN-ON-SPEY
Prepared by: Gavin Miles, Head of Planning and Communities
Recommendation
That the Planning Committee agree to refuse planning permission unless the associated restoration bond is secured by 26 July 2019.
Reason for recommendation
The Planning Committee agreed to approve the above application at its meeting on
17 August 2018 subject to conditions and a restoration bond (https://cairngorms.co.uk/resource/docs/boardpapers/17082018/Item6AABroomhillQ uarry20180140DET.pdf).
Since then there have been ongoing discussions between the operator and CNPA on
the provision of a suitable restoration bond so the formal decision notice has not yet been issued. Officers had expected the matters to be concluded quickly and have given oral updates to Planning Committee over the past months. We continue to expect this matter to be concluded soon as the operator has indicated they will provide a cash bond to the CNPA, which may be completed before this Committee Meeting.
However, as the matter has drawn out over a number of months, officers now
consider it appropriate to ask the Planning Committee to provide extra weight to draw matters to conclusion and allow the formal decision notice to be issued. We therefore request that the Planning Committee agree that unless the restoration bond and legal agreement are secured by 26 July 2019 (four weeks from this Planning Committee Meeting), the CNPA will refuse the application and take any enforcement action necessary.
Gavin Miles June 2019 gavinmiles@cairngorms.co.uk