Paper 2 Annex 2 C2030 Programme Risk Register
Project: C2030 Programme Project Manager: David Clyne Job title: Head of Cairngorms 2030 Date of last risk review: 22-Feb-24 Cairngorms 2030: Programme risk Period: Q2 2026
Audit and Risk Committee Paper 2 Annex 2 02 October 2026
Risk Matrix Key
- Rare (Low) 1
- Unlikely (Low) 2
- Possible 3
- Likely (High) 4
- Almost Certain (High) 5
| Risk ID No. | Date | Risk Description | Impact Description | Impact Level | Probability Level | Priority Level | Trend | Mitigation Strategy | Q1 25 | Q2 25 | Q3 25 | Q4 25 | Q1 26 | Q2 26 RAG Status | Status | Owner | Date of last assessment | Reassessment Date | Forward look to Q3 26 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 14/12/2023 | Delivery of Transport Scotland funded projects match funding for the programme is not secured at the values or within the timelines required to achieve project objectives. | Transport Scotland funding for 2026⁄27 remains unconfirmed and there is no confirmed date for notification despite continued engagement, including at Chief Executive level. The uncertainty continues to affect delivery sequencing, partner confidence and the ability to move several infrastructure projects from design into construction. | 5 | 3 | 15 | No change | Positive meeting held with TS. Costs resubmitted for assessment with decision likely in September 2026. Project teams are progressing design, approvals and preparatory activity wherever possible while the funding decision remains outstanding. | Amber | Red | Amber | Amber | Amber | Amber | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | Programme will have confirmed position on TS funding. Team ready for delivery at late notice and contractor in place to start works. Transport project priorities review in progress to respond to funding position. Latest update from Transport Scotland positive — revised costs submitted. Aim to return RAG status to green by year end. Future risk confidence remains at amber given uncertainties around transport funding referenced above and other partner funding streams which remain to be finalised. |
| 1 | 14/12/2023 | Total programme risk profile | Potential loss of match funding or partner support. | 5 | 3 | 15 | No change | Programme level risk remains Green. The principal areas requiring active management are Transport Scotland funding uncertainty and the new Amber position for Nature Recovery and Peatland Restoration. | Amber | Amber | Green | Green | Amber | Amber | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | Aim to return RAG status to green by year end. Match funding updates or delivery secured from public sector partners. |
| 2 | 14/12/2023 | Future funding profile | Insufficient match funding to meet agreed commitments. | 5 | 3 | 15 | No change | Future risk remains Amber because Transport Scotland funding and several partner match funding streams remain unresolved. The programme cash flow will be updated following confirmation of transport and landscape funding decisions. | Amber | Amber | Green | Green | Amber | Amber | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | Revised cost and match funding plan prepared. Aim to return RAG status to green by year end. |
| 3 | 14/12/2023 | Finance: impact on Park Authority budget management | Park Authority spend agreed at £450k pa. | 4 | 1 | 4 | Improving | No significant impact on the Park Authority budget is currently identified. Potential implications remain within the total agreed programme budget and will be managed through re-profiling and formal change control where required. | Green | Green | Green | Green | Green | Green | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | Overall budget management impacts remain within the total agreed budget. Revised cost and match funding plan prepared. |
| 4 | 14/12/2023 | Procurement standards | All contracts must meet PCS standards. Possible legal challenge if regulations not met. | 3 | 2 | 6 | Improving | Procurement activity remains in place and is being managed through the agreed programme processes. | Green | Green | Green | Green | Green | Green | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | Procurement schedule for Q3 2026 in place. |
| 5 | 14/12/2023 | Staffing | Insufficient staff in post impacts project delivery, timescales and outcomes. | 4 | 2 | 8 | Improving | No programme wide staffing risk is currently identified, although communications capacity will require active management during wildfire response and planned staff changes in Q3 and Q4. | Amber | Green | Green | Green | Green | Green | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | No staff resource issues. |
| 6 | 15/12/2023 | Nature Recovery Peatland projects delivery delays | Delays confirming projects and wildfire impacts on Peatland delivery. | 4 | 3 | 12 | Deteriorating | Nature Recovery has moved from Green to Amber because woodland projects have not yet been confirmed. The main issue is the gap between available public funding and the actual cost of technically challenging woodland schemes, creating financial liability for landowners. Confirmed projects, costs and approval expected end September 2026 when RAG status moves back to green. Peatland Restoration has been assessed as Amber due to operational risks arising from the July wildfire and associated delivery uncertainty. The project remains on track to achieve its annual outputs through active contingency planning and identification of substitute sites where required. | Amber | OPEN | David Clyne | 02/09/2026 | 13/10/2026 | Woodland projects now approved in principle by NLHF. Discussions with project teams give confidence that work is on track to address all issues and return projects to green by end September. |