220211ResourcesCtteeBudgetMonitoringPaper1Annex2
CAIRNGORMS NATIONAL PARK AUTHORITY YEAR ENDED 31 MARCH 2022 Partner funded Programme Activity
| PARTNER FUNDED | ||||
|---|---|---|---|---|
| LEADER | T&G GPB Caper Delivery Heritage Total | |||
| LP 13 – 12999 HG 17 – 02368 HG 17 – 06106 Horizons | ||||
| HH 21- | ||||
| Staff costs | 69,190 | 141,698 23,586 234,475 | ||
| Staff costs recovered | -69,190 | -141,698 ‑23,586 ‑234,475 | ||
| 0 | 0 0 0 0 0 0 | |||
| Project costs | ||||
| Project management costs | 1,347 | 10,371 42 51,226 | 62,986 | |
| T&G management & maintenance | 7,727 | 7,727 | ||
| Project costs | 162,001 | 58,170 143,765 194,489 150,000 | 708,424 | |
| Project recoveries | -163,348 | -76,267 ‑143,807 ‑245,714 0 | -629,136 | |
| 0 | 0 0 0 150,000 | 150,000 |