ARC Paper 6 Annex 2 Cairngorms 2030 Risk management
Cairngorms 2030: Risk management Project: C2030 Programme Project Manager: David Clyne Job title: Head of Cairngorms 2030 Date of last risk review: 22-Feb-24
Cairngorms 2030: Programme risk Period: Q1 2026
Likelihood 1: Rare (Low) 2: Unlikely (Low) 3: Possible 4: Likely (High) 5: Almost
Outcome 1: Minor 2: Moderate 3: Significant 4: Major 5: Catastrophic
| No. | Date | Risk Description | Impact Description | Impact Level | Probability Level | Priority | Trend | Mitigation Strategy | Q1 25 | Q2 25 | Q3 25 | Q4 25 | Q1 26 | Status | Owner | Date of last assessment | Reassessment Date | Forward look to Q2 26 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 14/12/2023 | Delivery of Sustrans/Transport Scotland funded projects match funding for the programme is not secured at the values or within the timelines required to achieve project objectives. | Timescale for delivery retains amber delivery risk. Transport Scotland/active travel. | 5 | 2 | 10 | Improving | Transport Scotland design funding applications have been submitted for next stage. Design consultants retained to progress projects between TS funding stages. Park CEO raising issues with Scottish Government for early funding confirmation NLHF briefed on delivery options and potential impacts. A reprioritisation of transport theme projects will be completed by August / September once Transport Scotland funding decisions are communicated. | Amber | Red | Amber | Amber | Amber | OPEN | David Clyne | 14/05/2026 | 31/07/2026 | Programme will have clearer position on TS funding timeline. Transport project priorities review in progress to respond to funding position. |
| 1 | 14/12/2023 | Total programme risk profile | Programme delay or failure. Potential loss of match funding or partner support. | 5 | 2 | 10 | Improving | Transport Scotland design funding applications submitted. Potential risk escalation to Scottish Government. An updated cost now has been developed which assumes funding will be received in future quarters. | Amber | Amber | Green | Green | Green | OPEN | David Clyne | 14/05/2026 | 31/07/2026 | Future risk is set at amber given uncertainties around transport funding referenced above and other partner funding streams which remain to be finalised. |
| 2 | 14/12/2023 | Future funding profile | Insufficient match funding to meet agreed commitments. | 5 | 2 | 10 | Improving | A full financial reappraisal will be undertaken in August/September when key funding decisions on transport and other project areas will be better understood. Alternative match funding options for woodland expansion are being progressed. Senior managers now chasing outstanding match funding commitment. Quarterly cash flow and match funding monitoring review has been delivered with project leads and finance team. | Amber | Amber | Green | Green | Green | OPEN | David Clyne | 14/05/2026 | 31/07/2026 | Match funding updates or delivery secured from public sector partners. |
| 3 | 14/12/2023 | Finance: impact on Park Authority budget management | Park Authority spend agreed at £450k pa. | 4 | 1 | 4 | Improving | Procurement standards and project initiation approvals are being revised to improve compliance and decision making. | Green | Green | Green | Green | Green | OPEN | David Clyne | 14/05/2026 | 31/07/2026 | Overall budget management impacts remain within the total agreed budget. |
| 4 | 14/12/2023 | Procurement standards | All contracts must meet PCS standards. Possible legal challenge if regulations not met. | 3 | 2 | 6 | Improving | Workplans for 26⁄27 in place. | Green | Green | Green | Green | Green | OPEN | David Clyne | 14/05/2026 | 31/07/2026 | Procurement schedule for Q2 2026 in place. |
| 5 | 14/12/2023 | Staffing | Insufficient staff in post impacts project delivery, timescales and outcomes. | 4 | 2 | 8 | Improving | All staff in post with monthly 1 – 1 development reviews. Training and skills development discussed with staff and delivered. | Amber | Green | Green | Green | Green | OPEN | David Clyne | 14/05/2026 | 31/07/2026 | No staff resource issues. |