Item 7 Appendix 1 Plans 20260098DET Distillery Spey Dam Laggan

Cairngorms Nation­al Park Author­ity Ùgh­dar­ras Pàirc Nàiseanta a’ Mhon­aidh Ruaidh

Item 7 Appendix 1 12 June 2026 Page 1 of 3

Agenda item 7

Appendix 1

2026/0098/DET

Plans


scale in metres 1:2500 [Image: A detailed site plan titled Site Loc­a­tion Plan 1:2500” and Site Loc­a­tion Plan 1:1250” show­ing a river, roads, and vari­ous fea­tures. The map includes con­tour lines and is ori­ented with north at the top. On the right side, there is a title block with pro­ject details.] Site Loc­a­tion Plan 1:2500 Site Loc­a­tion Plan 1:1250 scale in metres 1:2500 Dubh 281.9m Drain Well Pond rack n 260.9m 0 ODOODO DO Bru­ach Mhór St Michael’s Chapel (site of) Buri­al Ground (dis­used) River Spey DOODO POOOOD DIST GEN­ER­AL WADE’S MIL­IT­ARY ROAS (TRACKY Dail na Ceardaich 258.5m WA OS/OB 3 May 23 As Noted@A0 Spey­side Dis­til­lers Dal­chully Estate Lag­gan PH20 1BU olli blair archi­tects 0125.PL.001 Site Loc­a­tion Plans PLAN­NING vol​liblair​.co​.uk olli@​olliblair.​co.​uk +44 (0)7500 601940


[Image: A land­scape plan titled Land­scape GA Plan” with a detailed lay­out of a dis­til­lery site, show­ing pro­posed and exist­ing fea­tures, plant­ing, and infra­struc­ture. A com­pre­hens­ive legend is included on the right side of the plan, detail­ing soft­works, hard­works, and fur­niture. Sev­er­al numbered cal­louts indic­ate spe­cif­ic areas or ele­ments on the plan.] Land­scape GA Plan Scale 1:1000 Road to Lag­gan River Spey riv­ate access road Soft­works Legend Refer to plant­ing plan erz/​22 36/P06

  • Mead­ow
    • Spe­cies rich grass­land across the site
    • Wild­flower mead­ow to entrance roads and spaces
  • Shrub/​herbaceous planting
    • A mix of biod­i­verse spe­cies as a field lay­er at key spaces
  • Hedges
    • 1.2m tall hedging
  • Wet­land planting
    • To ditches, swales, basins and wetlands
  • Water bod­ies
    • SuDS pond, cool­ing pond and exist­ing pond
  • Exist­ing con­i­fer­ous plant­a­tion retained
  • Exist­ing con­i­fer­ous plant­a­tion removed
  • Exist­ing Birch ripari­an wood­land retained
    • Extends small islands with­in the Spey
  • Pro­posed wood­land planting
    • See plant­ing plan for spe­cies specification
  • Spe­ci­men trees
    • Semi mature tree planting
  • Wider land­scape trees
    • Semi mature tree planting
  • Aven­ue trees
    • Semi mature tree planting
  • Exist­ing rock outcrop

Hard­works Legend

  • Asphalt roads
  • Insitu con­crete surfacing
  • Res­in bound gravel paths and parking
  • Self bind­ing gravel wider land­scape paths
  • Nat­ur­al stone paving
    • To entrance spaces at mar­ket­ing suite and distillery
  • Nat­ur­al stone sett paving
    • To key points along access road and along Gen­er­al Wades Road
  • Grasscrete
    • To edge of access road and fire access routes
  • Steps
    • Stone steps on wider land­scape path
  • Deck
    • Sus­pen­ded steel access deck to mar­ket­ing suite with balustrade

Bound­ar­ies & Fur­niture Legend

  • Nat­ur­al stone walls to match building
    • Entrance wall 1m high
    • Wall at office 1.5m high
  • Deer Fen­cing
    • 2.0m high stock fence on tim­ber posts
  • Double leaf gate
    • 1.5m high steel gate, ver­tic­al bar. 3.7m wide
  • Tim­ber benches
    • 3no.
  • Cycle stands
  • Over­head cables
    • See erz 22 36 S03 for fur­ther detail

James Mor­ton Street erz Lim­ited www​.erz​stu​dio​.co​.uk T/F: 0141 552 0888 erz All dimen­sions are to be 18/09/2003 Spey­side Dis­til­lery Was­house and SuDS

  1. Bin store: Tim­ber gate to front
  2. Low stone wall with integ­rated signage
  3. Vis­it­or entrance space with drop off bay and vis­it­or grasscrete park­ing bays set in wood­land. Steps down onto lower field path with adja­cent ter­raced cascade
  4. Path to Spey and field drain/​linear wetland:
  5. Mar­ket­ing suite: Refer to Architect’s information
  6. Access bridge over Gen­er­al Wades Road: Refer to Architect’s information
  7. Dis­til­lery: Refer to Architect’s information
  8. SuDS pond with over­flow to wet­land to south
  9. Cool­ing pond with wet­land overflow
  10. Cool­ing tower: Refer to Architect’s information
  11. Power house: Refer to Architect’s information
  12. Inground fuel tanks with stan­doff and access path
  13. Mound­ing adja­cent to cool­ing pond to assist with visu­al screening
  14. Sprink­ler tanks: Refer to Engineer’s information
  15. Pipie bridge: Refer to Engineer’s information
  16. Ware­houses: Refer to Architect’s information
  17. Tank: Refer to Engineer’s information
  18. Office: Refer to Architect’s information
  19. SuDS basin planted with wet­land margins
  20. Swale
  21. Exist­ing pond/​wetland: New check damn at out­let to man­age water flow
  22. 2no. EV Char­ging bays
  23. Bike shel­ter

PLAN­NING 1:1000 A1 19/09/2023